State Route 47 Schuyler Heim Bridge Replacement

 

 

 

 

 

THE PROJECT
The lift-span portion of the existing Schuyler Heim Bridge will be replaced by a fixed-span bridge structure, which means the new span that expands over the navigation channel will permanently be attached to the support beams, as opposed to being able to move and lift upward. It has been determined to be more cost effective to replace the structure than attempt to retrofit the bridge. The project location limits are between Ocean Boulevard and 1/4 mile south of State Route 103 in the cities of Long Beach and Los Angeles. The bridge will have six lanes, three in each direction, and a 3/4 mile span.

SUMMARY

Constructed in 1946, the existing lift-span bridge will be replaced by a fixed span structure that will conform to higher seismic standards, enhancing safety. Additionally, replacing a deteriorating structure with a new one will also reduce maintenance costs and lead to improved roadway connections in the future.

The bridge will be constructed in stages:
1. Stage one involves construction of the northbound portion over Cerritos Channel, expected to take approximately six months;
2. Stage two will shut down the northbound half of the existing bridge, shifting traffic to the existing southbound section;
3. Stage three will shift traffic to the newly completed northbound bridge, demolish the remainder of the existing bridge and construct the southbound portion;
4. Stages four, five and six will consist of finishing work.

BENEFITS
The new bridge will provide a permanent navigable channel that is 180 feet wide with a vertical clearance of 47 feet to allow for the passage of ships. With the elimination of the lift, traffic will no longer be delayed due to passing ships. Replacing the lift-span bridge with a fixed-span bridge that meets current seismic standards will improve safety and benefit the local, state and national economy and internation trade.

 

COST
$351.3 million

 

SCHEDULE
Construction, which began in late 2011, is anticipated to complete in 2017.

 

Project Fact Sheet (PDF)

Heim Bridge Replacement Mitigation Truck Program FAQs (PDF) New