ea: 291304

Route: 33     County: VEN     Work:
Mile Post Beg./End: 7.6
Location: IN VEN CNTY ON RTE 33 AT SAN ANTONIO CREEK
Detailed Project Scope: SUB-SCOUR MIT AND RAILING UPGRADE
Estimate Cost Range (x $million) 1 - 10
Working Days Range: 600
Proposed Advertisement Date: 2016-08-01
Comments: PSSR estimate. No structure Q's listed.
Types Of Work  
Arrow Bridge Railing
Arrow Bridge
Quantity Of Major Highway Items  
Asphalt Condrete (Tons) 0
PCC (cy) 0
Aggregate Base (cy) 0
Imported Borrow (cy) 0
Roadway Excavation (cy) 0
Major Structure Items  
Steel (lbs): 0
PCC (cy): 0

Page Last Modified 03/5/13 08:58