ea: 286704
Route:
1
County:
LA
Work:
| Mile Post Beg./End: | 07.7 /09.2 |
| Location: | PROJ DOMINGUEZ CHENNEL VAR TMDLS(LA 1 PM7.7-9.24,LA91 PM6-8.43,LA105, |
| Detailed Project Scope: | IMPLEMENT STORM WATER TREATMMENT |
| Estimate Cost Range (x $million) | 60 - 80 |
| Working Days Range: | 750 |
| Proposed Advertisement Date: | 2017-03-01 |
| Comments: | The project will install GSRDs at eight locations, bio-swales/strips at 57 locations, media filters at 23 locations, an infiltration basin at one location, and a detention device at one location. |
| Types Of Work |
| Earthwork |
| Erosion Control |
| Highway Planting |
| Irrigation System |
| Quantity Of Major Highway Items |
| Asphalt Condrete (Tons) | 0 |
| PCC (cy) | 0 |
| Aggregate Base (cy) | 0 |
| Imported Borrow (cy) | 0 |
| Roadway Excavation (cy) | 1815690 |
| Major Structure Items |
| Steel (lbs): | 0 |
| PCC (cy): | 0 |