ea: 202124

Route: 710     County: LA     Work:
Mile Post Beg./End: 21.9/23.1
Location: IN CMMRC & BLL FRM SOUTH ATLNTC BLV TO TRIGGS ST REHAB RDWY
Detailed Project Scope: LONG LIFE PAVEMENT & WIDEN BRIDGES
Estimate Cost Range (x $million) 80 - 100
Working Days Range: 650
Proposed Advertisement Date: 2014-06-01
Comments: Quanties are rough.
Types Of Work  
Arrow Bridge
Arrow Replace PCC Pavement
Arrow Widening
Quantity Of Major Highway Items  
Asphalt Condrete (Tons) 0
PCC (cy) 26800
Aggregate Base (cy) 15800
Imported Borrow (cy) 0
Roadway Excavation (cy) 123000
Major Structure Items  
Steel (lbs): 0
PCC (cy): 0