ea: 1193U4

Route: 010     County: LA     Work:
Mile Post Beg./End: 37.5/42.4
Location: IN LA COUNTY FROM CITRUS STREET IN WEST COVINA TO ROUTE 57 IN POMONA
Detailed Project Scope: CONSTRUCT HOV LANE IN EACH DIRECTION
Estimate Cost Range (x $million) 120 - 140
Working Days Range: 940
Proposed Advertisement Date: 2014-10-01
Comments: 119334 combined with 289004 (Major Rehab)
Types Of Work  
Arrow Freeway and Structures
Arrow Widening
Quantity Of Major Highway Items  
Asphalt Condrete (Tons) 54000
PCC (cy) 66700
Aggregate Base (cy) 91000
Imported Borrow (cy) 0
Roadway Excavation (cy) 206000
Major Structure Items  
Steel (lbs): 13000000
PCC (cy): 76000