California Department of Transportation

Office of California Transportation Commission Liaison (OCTCL)

2003 "FP" Resolutions


Resolution
Status
Date Passed
Title/Description

FP-03-07

Amending Resolution
FA-02-09

August 14, 2003
Ref. No. 2.9b.
Tab 89

Technical Change for one Assembly Bill 608 adjustment for one STIP Project on the State Highway System approved in May 2003. The adjustment allocation is being revised from $21,977,351 to $25,865,000 to correct an error in reading the funding plan from the project sponsor.

FP-03-08

Original

August 14, 2003 Ref. No. 2.9a.
Tab 45

Technical change to delegated allocation for one Local Assistance STIP project for Project Development Components of Local Grants Projects in the City of Trinidad originally allocated on August 13, 2001 in the amount of $32,000 and reported to the Commission under reference number 2.5f.(5) on October 3-4, 2001. This project is being revised to show the correct funding for construction and PS&E components. Construction is being revised from $32,000 to $19,000. No change in total project allocation amount.

FP-03-09

Original

August 14, 2003
Ref. No. 2.5b.(6)
Tab 59

Financial Allocation for One SHOPP Project designated for allocation in the Proposed
FY-03-04 Allocation Plan totaling $950,000.

FP-03-10
Original
Sept. 24-25, 2003
Ref. No. 2.5a.(3)
Tab 60
Financial Allocation for Three Minor SHOPP Safety Projects totaling $2,030,000.
FP-03-13
Original
Oct. 29-30, 2003
Ref. No. 2.5a.(3)
Tab 38
Financial Allocation for Five Minor SHOPP Safety Projects totaling $2,874,000 plus $625,000 from other sources.
FP-03-14
Original
Oct. 29-30, 2003
Ref. No. 4.3a.
Tab 68
Six SHOPP TEA Projects totaling $3,042,000 allocated off the Pending Allocation List.
FP-03-15
Original
Oct. 29-30, 2003
Ref. No. 4.3a.
Tab 68
Four Local STE Projects totaling $2,274,132 allocated off the Pending Allocation List.
FP-03-16
Original
Dec. 11, 2003
Ref. No.2.5a.(3)
Tab 43
Finanical Allocation for Seven Minor SHOPP Safety Projects totaling $2,796,000 plus $491,000 from other sources.
FP-03-17
Original
Dec. 11, 2003
Ref. No. 2.5a.(4)
Tab 44
Financial Allocation for One Minor SHOPP Project for $500,000.
FP-03-18
Original
Dec. 11, 2003
Ref. No. 2.5b.(2)
Tab 73
Financial Allocation for 14 SHOPP Projects on the proposed FY-03-04 SHOPP Allocation Plan totaling $26,433,000.
FP-03-19
Original
Dec. 11, 2003
Ref. No. 4.3a.
Tab 78
Six SHOPP Projects totaling $72,800,000 Voted Off the Pending Allocation List.
FP-03-20
Original
Jan. 22, 2004
Ref. No. 2.5a.(3)
Tab 52
Financial Allocation for Five Minor SHOPP Safety Projects totaling $1,730,000 plus $82,000 from other sources.
FP-03-21
Original
Jan. 22, 2004
Ref. No. 2.5a.(4)
Tab 35
Financial Allocation for Two Minor Projects totaling $816,000.
FP-03-22
Original
Jan. 22, 2004
Ref. No. 2.5b.(2)
Tab 53
Finanical Allocation for Five SHOPP Projects on the proposed FY-2003-04 SHOPP Allocation Plan totaling $17,544,000.
FP-03-23
Original
Jan. 22, 2004
Ref. No. 2.5b.(3)
Tab 54
Financial Allocation for Two SHOPP Projects Amended into the SHOPP by Departmental action totaling $2,290,000.
FP-03-24
Original
Jan. 22, 2004
Ref. No. 2.5b.(4)
Tab 36
Financial Allocation for One SHOPP Managed TEA Project on the State Highway System for $125,000 plus $690,000 from other sources.
FP-03-25
Original
Jan. 22, 2004
Ref. No. 2.5c.(3)
Tab 61
Financial Allocation for 19 Local Assistance Environmental Enhancement and Mitigation (EEM) Projects totaling $5,000,000 plus $35,646,262 from other sources.
FP-03-26
Original
Jan. 22, 2004
Ref. No. 4.3a.
Tab 59
46 SHOPP Projects totaling $95,084,000 in State and Federal funds as well as $5,879,000 in Federal ER Funds for a total of $100,963,000 Voted Off the Pending Allocation List.
FP-03-27
Original
Feb. 26, 2004
Ref. No. 2.5a.(1)
Tab 55
Financial Allocation for 36 Minor Projects on the FY-03-04 SHOPP Allocation Plan totaling $18,297,000 plus $1,122,000 from other sources.
FP-03-28
Original
Feb. 26, 2004
Ref. No. 2.5a.(3)
Tab 40
Financial Allocation for 11 Minor Safety Projects totaling $4,732,000 plus $99,000 from other sources.
FP-03-29
Original
Feb. 26, 2004
Ref. No. 2.5b.(2)
Tab 57
Financial Allocation for Eight SHOPP Projects on the FY-03-04 SHOPP Allocation Plan totaling $24,323,000 pluls $795,000 from other sources.
FP-03-30
Original
Feb. 26, 2004
Ref. No. 2.5b.(3)
Tab 58
Financial Allocation for One SHOPP Project Amended into the SHOPP by Departmental action for $8,000,000 $8,350,000.
FP-03-31
Original
Feb. 26, 2004
Ref. No. 2.5b.(4)
Tab 41
Financial Allocation for Two SHOPP Managed TEA Projects on the FY-03-04 Allocation Plan totaling $2,801,000 $3,181,000 plus $1,461,000 $2,502,000 from other sources.
FP-03-32
Original
Feb. 26, 2004
Ref. No. 2.5c.(2)
Tab 42
Financial Allocation for Three Local Assistance STIP Projects off the State Highway System totaling $2,432,000 plus $7,434,000 from other sources.
FP-03-33
Original
Feb. 26, 2004
Ref. No. 2.5c.(8)
Tab 67
Financial Allocation for Nine Local Assistance STIP Projects for Planning, Programming and Monitoring totaling $415,000.
FP-03-34
Original
Feb. 26, 2004
Ref. No. 2.5c.(11)
Tab 43
Financial Allocation for One Local Assistance Statewide Transportation Enhancement (STE) Project for $60,000.
FP-03-35
Original
Feb. 26, 2004
Ref. No. 2.5g.
Tab 44
One Eureka Non-Freeway Alternative Project in Humboldt County for $1,222,000.
FP-03-36
Original
Feb. 26, 2004
Ref. No. 4.3a.(1)
Tab 69
30 PPM projects totaling $2,959,000 and one TE project for $20,000 voted off the pending allocation list.
FP-03-37
Original
Feb. 26, 2004
Ref. No. 4.3a.(2)
Tab 69
28 SHOPP projects totaling $59,807,000 voted off the pending allocation list.
FP-03-38
Original
April 8, 2004
Ref. No. 2.5a.(1)
Tab 29
Financial Allocation for 11 Minor Projects on the FY-03-04 SHOPP Allocation Plan totaling $5,161,000.
FP-03-39
Original
April 8, 2004
Ref. No. 2.5a.(3)
Tab 30
Financial Allocation for 17 Minor Safety Projects totaling $7,476,400 plus $77,000 from other sources.
FP-03-40
Original
April 8, 2004
Ref. No. 2.5b.(2)
Tab 48
Financial Allocation for 30 SHOPP Projects totaling $135,175,000.
FP-03-41
Original
April 8, 2004
Ref. No. 2.5b.(3)
Tab 31
Financial Allocation for One SHOPP Project Amended into the SHOPP by Departmental action for $4,200,000.
FP-03-42
Original
April 8, 2004
Ref. No. 4.3a.(1)
Tab 49
Eight SHOPP projects totaling $24,777,000 voted off the Pending Allocation List.
FP-03-43
Original
May 13, 2004
Ref. No. 2.5b.(1)
Tab 57
Financial Allocation for Three Minor Projects totaling $847,000 plus $934,300 from other sources.
FP-03-44
Original
May 13, 2004
Ref. No. 2.5a.(3)
Tab 35
Financial Allocation for 11 Minor SHOPP Safety Projects totaling $3,231,000 plus $360,000 from other sources.
FP-03-45
Original
May 13, 2004
Ref. No. 2.5b.(2)
Tab 36
Financial Allocation for 15 SHOPP Projects on the FY-03-04 SHOPP Allocation Plan totaling $61,104,000.
FP-03-46
Original
May 13, 2004
Ref. No. 2.5b.(3)
Tab 37
Financial Allocation for Three SHOPP Projects Amended into the SHOPP by Departmental action totaling $13,814,000.
FP-03-47
Original
May 13, 2004
Ref. No. 2.5b.(4)
Tab 38
Financial Allocation for Two SHOPP Managed TEA Projects designated for allocation on the FY-03-04 Allocation Plan totaling $485,000.
FP-03-48
Original
May 13, 2004
Ref. No. 2.5c.(2)
Tab 66
Financial Allocation for One Local Assistance Statewide Transportation Enhancements (STE) Project for $980,868.
FP-03-49
Original
May 13, 2004
Ref. No. 2.5b.(7)
Tab 50
Financial Allocation for One STIP Transportation Enhancement project for $23,000,000, plus $2,980,000 from other sources.
FP-03-51
Original
June 17, 2004
Ref. No. 2.5a.(1)
Tab 43
Financial Allocation for Nine Minor Projects on the FY 2003-04 SHOPP Allocation Plan totaling $3,570,000 plus $2,400,000 from other sources.
FP-03-52
Original
June 17, 2004
Ref. No. 2.5a.(3)
Tab 44
Financial Allocation for Eight Minor SHOPP Safety Projects on the FY 2003-04 SHOPP Allocation Plan totaling $3,632,000 plus $285,000 from other sources.
FP-03-53
Original
June 17, 2004
Ref. No. 2.5a.(4)
Tab 66
Financial Allocation for One Minor SHOPP Safety Project for $630,000. (Related item under 2.4a.(3).)
FP-03-54
Original
June 17, 2004
Ref. No. 2.5b.(2)
Tab 45
Financial Allocation for 15 SHOPP Projects on the FY 2003-04 SHOPP Allocation Plan totaling $95,647,000.
FP-03-55
Original
June 17, 2004
Ref. No. 2.5b.(3)
Tab 46
Financial Allocation for Seven SHOPP Projects totaling $13,271,000 Amended into the SHOPP by Departmental action.
FP-03-56
Original
June 17, 2004
Ref. No. 2.5b.(4)
Tab 47
Financial Allocation for One SHOPP Managed TEA Project for $1,613,000.
FP-03-57
Original
June 17, 2004
Ref. No. 2.5c.(3)
Tab 48
Financial Allocation for Three Local Assistance Environmental Enhancement and Mitigation (EEM) Projects totaling $988,244 plus $2,003,186 from other sources.
FP-03-58

Amending Res FP-03-25

June 17, 2004
Ref. No. 2.5c.(10)
Tab 49

Financial Allocation Amendment for Four Local Assistance Environmental Enhancement and Mitigation (EEM) Projects totaling ($988,244).

FP-03-59
Original
June 17, 2004
Ref. No. 2.5b.(6)
Tab 79
Financial Allocation for Eight SHOPP Projects totaling $24,333,000 above the line but not fundable at this time.