Transportation Programming Links
Office of California Transportation Commission Liaison (OCTCL)
2002 "WAIVER" Resolutions
| Resolution |
Status |
Date
Passed |
Title/Description
|
| WAIVER-02-01 |
Original |
Jan
23, 2002 |
Request to Extend the Period of Contract Award for one local STIP project for the Sacramento Regional Transit Fourth St./Wayne Hultgren Station for $50,000. |
| WAIVER-02-02 |
Original |
Jan
23, 2002 |
Request to Extend the Period of Contract Award for one local STIP project in the City of Arroyo Grande for $419,000. |
| Original |
Jan
23, 2002 |
Request to Extend the Period of Contract Award for one Proposition 116 intercity rail project for the NCtd’s Encinitas Passing Track for $3,000,000. |
|
| WAIVER-02-04 |
Original |
Jan
23, 2002 |
Time Extension Requests for Second Cycle CMAQ (12 projects totaling $12,405,237) and Regional TEA Funds (12 projects totaling $4,950,069). No time extension requests were made for Second Cycle RSTP funds. |
| WAIVER-02-05 |
Original |
Feb.
28, 2002 |
Request to Extend the Period of Project Allocation for three local STIP projects for Sierra County for $530,000. |
| WAIVER-02-06 |
Original |
Feb.
28, 2002 |
Request to Extend the Period of Project Allocation for one STIP project in Butte County for $50,935,000. |
| WAIVER-02-07 |
Original |
Feb.
28, 2002 |
Request to Extend the Period of Contract Award for two local STIP projects for the cities of Monterey and Grover Beach for $1,293,000. |
| WAIVER-02-08 |
Original |
Apr.
3, 2002 |
Request to Extend the Period of Project Allocation for two local STIP projects for the City of Pasadena and Ventura County for $1,864,000. |
| WAIVER-02-09 |
Original |
Apr.
3, 2002 |
Request to Extend the Period of Project Allocation for one local STIP project on the State Highway System in Madera County for $3,400,000. |
| WAIVER-02-10 |
Original |
Apr.
3, 2002 |
Request to Extend the Period of Project Reimbursement for four local STIP projects for the cities of Fremont and Shafter, and Santa Barbara County for $5,015,000. |
| WAIVER-02-11 |
Original |
May.
9, 2002 |
Request to Extend the Period of Project Allocation for 18 local STIP projects for $41,723,000. Two of these (#16 and 17) are also requesting to shift of funds between components. Project #7 – Revised Extension Amount from $75,000 to $30,000. |
| WAIVER-02-12 |
Original |
May.
9, 2002 |
Request to Extend the Period of Project Allocation for one local STIP project for the City of Los Angeles for $100,000. Withdrawn at the Meeting – Return in June. |
| WAIVER-02-13 |
Original |
May.
9, 2002 |
Request to Extend the Period of Project Allocation for two local STIP projects for the City of Needles and North County Transit District (NCtd) for $3,715,000. |
| WAIVER-02-14 |
Original |
May.
9, 2002 |
Request to Extend the Period of Project Allocation for one local STIP project, Sorrento to Miramar Double Track Project in San Diego County, for North County Transit District (NCtd) for $21,390,000 for Phase One and $5,300,000 for Phase Two. |
| WAIVER-02-15 |
Original |
May.
9, 2002 |
Request to Extend the Period of Contract Award for two local STIP projects for the City of Avalon and Los Angeles County for $1,290,000. |
| WAIVER-02-16 |
Original |
May.
9, 2002 |
Request to Extend the Period of Contract Award for two local STIP projects in the cities of El Paso De Robles and Dunsmuir for $876,000. |
| WAIVER-02-17 |
Original |
May.
9, 2002 |
Request to Extend the Period of Project Completion for one local STIP project for North County Transit District for $3,600,000. |
| WAIVER-02-18 |
Original |
May.
9, 2002 |
Request to Extend the Period of Project Completion for one local STIP project for San Diego Metropolitan Transit Development Board for $368,000. |
| WAIVER-02-19 |
Original |
May.
9, 2002 |
Request to Extend the Period of Project Completion for one local STIP project for the Rocklin Station Design for Placer County Transportation Planning Agency for $150,000. |
| WAIVER-02-20 |
Original |
May.
9, 2002 |
Request to Extend the Period of Project Reimbursement for four local STIP projects for Trinity County, Alameda County Transportation Authority, and Santa Cruz County Regional Transportation Commission for $4,789,000. |
| WAIVER-02-21 |
Original |
June
13, 2002 |
Request to Extend the Period of Project Allocation for 32 local STIP projects for $32,362,970. Project #30 for San Joaquin County is also requesting shifting of funds between components. |
| WAIVER-02-22 |
Original |
June
13, 2002 |
Request to Extend the Period of Project Allocation for one local STIP project for the City of Los Angeles for $100,000. |
| WAIVER-02-23 |
Original |
June
13, 2002 |
Request to Extend the Period of Project Allocation for seven STIP projects in Los Angeles County, totaling $25,503,000. |
| WAIVER-02-24 |
Original |
June
13, 2002 |
Request to Extend the Period of Project Allocation for the construction component of one STIP project on Route 101 in Santa Barbara County (PPNO 0481), originally programmed for $2,264,000 in FY 2001-02 and $836,000 FY 2002-03. |
| WAIVER-02-25 |
Original |
June
13, 2002 |
Request to Extend the Period of Project Allocation for 18 months for the construction component of one STIP Intercity Rail Station project for the City of Oxnard (PPNO 9877), originally programmed in FY 2001-02 for $1,081,000. |
| WAIVER-02-26 |
Original |
June
13, 2002 |
Request to Extend the Period of Project Allocation for 12 months for the construction component of one STIP Intercity Rail project, for Bandini DT Junction Track project for the Pacific Surfliner Corridor (PPNO 2000), originally programmed in FY 2001-02 for $5,700,000. |
| WAIVER-02-27 |
Original |
June
13, 2002 |
Request
to Extend the Period of Project Allocation for 6 |
| WAIVER-02-28 |
Original |
June
13, 2002 |
Request to Extend the Period of Project Allocation for two local STIP projects for San Francisco Bay Area Rapid Transit District PPNO 04-1035) and City of Santa Clarita (PPNO-07-2901) totaling $223,000. |
| WAIVER-02-29 |
Original |
June
13, 2002 |
Request to Extend the Period of Contract Award for eight local STIP projects for $4,918,000. |
| WAIVER-02-30 |
Original |
June
13, 2002 |
Request to Extend the Period of Contract Award for two local STIP projects for the City of Inglewood (PPNO 07-2908) and City of South Pasadena (PPNO 07-2913) totaling $1,060,000. |
| WAIVER-02-31 |
Original |
June
13, 2002 |
Request to Extend the Period of Project Reimbursement Request to Extend the Period of Project Reimbursement for Two local STIP projects for City of Delano and Alameda Corridor- East Construction Authority for $2,991,000. |
| WAIVER-02-32 |
Original |
July
18, 2002 |
Post Fact Request to Extend the Period of Reimbursement for 20 months for the Right of Way and Design elements of one local TCI project for the City of Indio – Downtown Intermodal Center (PPNO 08-5131), originally allocated $381,000 in FY 1998-99. |
| WAIVER-02-33 |
Original |
June
13, 2002 |
Request to Extend the Period of Reimbursement for 18 months for one Proposition 116 project for Trinity County - Hayfork Park and Ride (PPNO 02-2165), originally allocated $41,037 in FY 1999-00. |
| WAIVER-02-34 |
Original |
June
13, 2002 |
Request to Extend the Period of Project Allocation for one local STIP project in the City of Glendale (PPNO 07-9814) for $16,375,000. |
| WAIVER-02-35 |
Original |
July
18, 2002 |
Post
Fact Request to Extend the Period of Contract Award |
| WAIVER-02-36 |
Original |
July
18, 2002 |
Request to Extend the Period of Project Reimbursement for 2 local STIP projects in the City of San Jose for $108,000. |
| WAIVER-02-37 | Original |
Aug.
22, 2002 Ref. No. 2.8b. Tab 81 |
Post Fact Request to Extend the Period of Contract Award for seven months for one local STIP project in the City of San Buenaventura for $460,000. |
| WAIVER-02-38 | Original | Aug.
22, 2002 Ref. No. 2.8c. Tab 82 |
Post Fact Request to Extend the Period of Project Completion for four months for the City of Grass Valley's Bike Racks project for $4,500 in FY 1999-00. |
| WAIVER-02-39 | Original | Oct.
3, 2002 Ref. No. 2.8b.(1) Tab 77 |
Request to Extend the Period of Contract Award for a local STIP project (PPNO 2368) in the City of Burbank for $4,636,000. |
| WAIVER-02-40 | Original | Oct.
3, 2002 Ref. No. 2.8b.(2) Tab 78 |
Request to Extend the Period of Contract Award for a local STIP project (PPNO 2368) in the City of Burbank for $4,636,000. |
| WAIVER-02-41 | Original | Oct.
3, 2002 Ref. No. 2.8d. Tab 79 |
Request to Extend the Period of Project Reimbursement for a local STIP project (PPNO 3011R) in the City of Clearlake for $51,000. |
| WAIVER-02-42 | Original | Nov.
7, 2002 Ref. No. 2.8b.(1) Tab 63 |
Request to Extend the Period of Contract Award - Three projects in the Cities of Atascadero and Goleta, and the County of Santa Barbara totaling $2,834,000. |
| WAIVER-02-43 | Original | Nov.
7, 2002 Ref. No. 2.8b.(2) Tab 64 |
Request
to Extend the Period of Contract Award - Post Fact Requests
for |
| WAIVER-02-44 | Original | Nov.
7, 2002 Ref. No. 2.8c. Tab 65 |
Request to Extend the Period of Project Completion for 20 months for one local STIP project for the San Francisco Bay Area Rapid Transit District's Advanced Automatic Train Control project, originally allocated $41,220,000 on July 15, 1999 from PPNOs 04-2112, 04-2121, 04-2139, and 04-2143. |