CAPITAL SUPPORT PERFORMANCE MEASURES

I.  PROGRAM PERFORMANCE MEASURES FOR CAPITAL SUPPORT

A.  Background

In December 1995, the Department submitted its REPORT TO THE LEGISLATURE ON CAPITAL SUPPORT PERFORMANCE MEASURES in response to supplemental report language in the 1995 Budget Act. This report proposed twelve measures for evaluating all major capital outlay support functions. The budget language stated that the proposed measures must provide an accurate measure of annual efficiency, provide a consistent basis for year-to-year comparison, and evaluate both the Departmentís cost and timeliness in completing work.

In the Departmentís three-tiered scheme of measures, these twelve capital support performance measures are program measures for the statewide Capital Outlay Support (COS) Program. Their relationship to corporate measures will be described later in this report.

The purpose of this report is to summarize the status of the capital outlay support performance measures, report data for these measures for the past few years, where available, and recommend targets, where possible. Much data is involved in these measures from the project level to the department level. This report will address the measures only to the department level.

B.  Context of Capital Support in the Department

Performance Measure #1 of the Report to the Legislature proposed "pie" charts showing PY and dollar expenditures for the Departmentís programs, the elements of the Highways program, and the parts of capital support. This is not a performance measure as such, but rather it sets the context for the other measures. For the purpose of this summary report, a few of these charts are shown to set the context.

In FY 1995/96, total Caltrans expenditures were $4.35 billion of which $3.98 billion or 91% were Highways Program expenditures. The dominance of the Highways Program is shown in the following chart:


 Column chart Caltrans Project Management from 1995 to 1996 by activity and percent expenditure
1995/96 Capital Support Expenditures by Activity Category
Activity Category Dollars Expenditure
Aeronautics $7,321,302
Highways $3,976,530,160
Mass Transportation $321,978,142
Transportation Planning $42,574,738

Of the $3.98 billion in Highways Program expenditures, capital support represents $690 million and capital outlay $1,812 million. The percentages for these and the other elements of the Highways Program are shown below:


Pie chart of Caltrans Project Management from 1995 to 1996 by program element and percent expenditure

1995/96 Capital Support Expenditures by Activity Category and Percent Expenditure
Activity Category Percent Expenditure
Maintenance 12%
Operations 3%
Legal Services 1%
Administration 5%
Planning & Research 1%
Local Assistance 12%
State/Local Partnership 2%
Capital Support 17%
Capital Outlay 46%

C.  Relationship of Capital Support to Capital Outlay

Flow chart of Caltrans Project Management from 1988 to 1996 by activity and percent expenditure
1988/89 through 1995/96 Capital Support Expenditures by Activity Category and Percent Expenditures
Capital Support Category FY 88/89 FY 89/90 FY 90/91 FY 91/92 FY 92/93 FY 93/94 FY 94/95 FY 95/96
Construction 14% 12% 12% 14% 15% 15% 15% 12%
Design & Right of Way 20% 20% 19% 21% 24% 17% 19% 19%
Preliminatry/Environmental 12% 10% 11% 9% 8% 4% 4% 3%
State Program Capital Outlay Expenditures ---- ---- ---- ---- ---- ---- ---- ----
TOTAL ---- ---- ---- ---- ---- ---- ---- ----

Target: Based on recent trends and Project Management Improvement efforts, the Project Management Program is recommending a goal of 33%.

It is important to note that the capital support and capital outlay expenditures represent different sets of projects at different times. Most capital support effort is expended on projects to be awarded in the future. Similarly, capital outlay is expended for projects developed in the past.