Restoring the Golden State

District 3
Contract for Delivery
FY 2006/2007

Ready to List (RTL) Milestone Delivery
Description 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Total
Number of Planned Deliveries 16 4 4 2 26
Number of Advanced Deliveries 0 4 3 0 7
Construction Value
($ Millions)
$47.0 $97.7 $52.9 $107.5 $305.1

District 3 commits to the delivery by quarter of the projects listed by Ready to List (RTL) milestones and dollar values as shown above.

Signed by, Jody E. Jones, District 3 Director, on 6/22/06

Signed by, Will Kempton, Director, on 6/22/06

Attachment: 2006/2007 FY Project RTL Baseline Delivery Plan