Restoring the Golden State

District 2
Contract for Delivery
FY 2006/2007

Ready to List (RTL) Milestone Delivery
Description 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Total
Number of Planned Deliveries 7 1 9 2 19
Number of Advanced Deliveries 1 0 1 1 3
Construction Value
($ Millions)
$19.4 $1.5 $23.6 $15.4 $59.9

District 2 commits to the delivery by quarter of the projects listed by Ready to List (RTL) milestones and dollar values as shown above.

Signed by, Brian Crane, District 2 Director, on 6/22/06

Signed by, Will Kempton, Director, on 6/22/06

Attachment: 2006/2007 FY Project RTL Baseline Delivery Plan