Restoring the Golden State

District 10
Contract for Delivery
FY 2006/2007

Ready to List (RTL) Milestone Delivery
Description 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Total
Number of Planned Deliveries 0 5 3 2 10
Number of Advanced Deliveries 1 0 0 2 3
Construction Value
($ Millions)
$2.8 $53.4 $27.2 $46.8 $130.2

District 10 commits to the delivery by quarter of the projects listed by Ready to List (RTL) milestones and dollar values as shown above.

Signed by, Kome Ajise, District 10 Director, on 6/22/06

Signed by, Will Kempton, Director, on 6/22/06

Attachment: 2006/2007 FY Project RTL Baseline Delivery Plan