California State Department of Transportation
Project Development Workflow Tasks (PDWT)
|
PYPSCAN Milestone 380
Send District PS&E to Office of Office Engineer
(Click on highlighted Task to see detailed information.)
TASK D422 (380.A)
Prepare Draft Contract Documents (Nonqualified
Projects)
Narrative
For projects that are "not qualified", the Office of Office
Engineer (OOE) is responsible for preparing the draft contract documents.
Initiator
Sub-Tasks
- After the Division of Structure's PS&E has been combined with the
district PS&E, transmit the combined PS&E submittal to the OOE.
- OOE prepares draft contract documents and sends to the district for
review.
Task Duration
References
TASK D423 (380.B)
Prepare Request for Funds
Narrative
An important step in preparing the final contract documents is to obtain
funding. A draft Request for Funds must be prepared and then reviewed by
the district. The Division of Budgets will submit the request to the CTC.
Initiator
Sub-Tasks
- Analyze the current Basic Engineering Estimating System estimate. Consider
size of project, inflation, time of the year, etc.
- Prepare a draft Request for Funds. Attach appropriate estimates.
- Circulate the draft Request for Funds to affected district units.
- Resolve comments, revise the Request for Funds, and submit to the Deputy
District Director for signature.
- Send the Request for Funds to the Division of Budgets.
- Attach copy to PS&E Submittal.
Task Duration
References
- Project Development Procedures Manual -- Section 3-50.30, Article 70
- Plans, Specifications and Estimates Guide -- Section 2-3.02S
- Tasks D408 and D420
TASK D424 (380.B)
Obtain CTC Funding Approval
Narrative
The Division of Budgets submits the Request for Funds to the CTC. The
Request for Funds should be submitted to Headquarters about six weeks in
advance of the CTC meeting scheduled for the funding vote.
Initiator
Sub-Tasks
- Schedule a funding vote date with the CTC.
- Send the Request for Funds to the CTC.
- Notify the district of the CTC vote.
Task Duration
References
TASK D425 (380.C)
Obtain FHWA Approval of PS&E for Interstate
System Projects
Narrative
PS&E Submittal and a FNM-76 for applicable projects on the Interstate
System are sent to the FHWA for approval.
Initiator
- Project Engineer and District Office Engineer (DOE)
Sub-Tasks
- Furnish the DOE with a complete PS&E Submittal.
- DOE sends the PS&E Submittal to FHWA and requests the HQ Federal-Aid
Section to send a FNM-76 to FHWA.
- The Office of Office Engineer sends a copy of the FHWA approval to
the DOE.
Task Duration
References
- Plans, Specifications and Estimates Guide -- Section 3-9
- Task D253