State of California  Business, Transportation and Housing Agency

M e m o r a n d u m

 To: DISTRICT DIRECTORS
DISTRICT DIVISION CHIEFS
DISTRICT OFFICE ENGINEERS
JOHN ALLISON, ESC
KAY GRIFFIN, ESC
MICKEY HORN, ESC
ELDON DAVISSON, ESC

Date : April 21, 2000

File:

 From: DEPARTMENT OF TRANSPORTATION
DIRECTORS OFFICE
MAIL STATION 49
 Subject: Processing English Unit Projects

There are still a limited number of projects that have received metric exceptions and have not been constructed. This memorandum outlines the plan and specification requirements associated with delivering a project in English units.

Project Plans:

  1. The latest design standards contained in the current Highway Design and Traffic Manuals, and other applicable design guidance must be used.
  2. All project references to the 1992 Standard Plans must be removed.
  3. Construction details previously covered in the 1992 Standard Plans must be converted from the current Metric Standard Plans. These are to be incorporated into the project plans as Construction Details under the seal and signature of the Responsible Charge Engineer. The Responsible Charge Engineer is advised to convert the entire Standard Plan sheet instead of incorporating specific details. Some details are part of larger systems with references across several Standard Plan sheets. Unless the entire sheet is converted, some details may be missed.

Project Specifications:

  1. The Responsible Charge Engineer must compare requirements between all applicable sections of the 1992 English and the current Metric Standard Specifications and Standard Special Provisions. There are significant differences between the 1992 versions and the current versions of these documents. These differences may not be readily apparent. A line-by-line comparison is recommended to avoid inconsistencies and errors.
  2. All applicable changes that have occurred between the two versions (1992 & current) of the Standard Specifications and Standard Special Provisions must be incorporated into the Project Special Provisions. This includes deleting requirements in the 1992 versions that are no longer applicable.

Current projects that have been granted an exception to use English units are listed in the attachment. Any projects that are being designed in English units that are not on the list will require processing a metric exception. You should anticipate that no new projects will be given an exception without complete justification.

Toll Seismic Retrofit projects currently in design phase, are provided a blanket metric exception. These projects are identified with an asterisk on the attached list. All of the plan/specification requirements outlined in this memo shall apply.

The effort required to deliver an English project should be discussed with the District Office Engineer, ESC Structure Design Office Engineer, and ESC Division of Office Engineer. Based on these discussions you may determine that it is more time and cost effective to deliver the project in metric units.

Encroachment permit projects (up to $1,000,000 in State right of way) may be delivered in dual units as indicated in the memorandum dated October 22, 1999, signed by Robert L. Buckley.

If you have any questions, please contact Terry Abbott, Metric Coordinator, at (916) 653-0253.

Original Signed By

BRENT FELKER
Deputy Director
Project Development

Attachment

Return to Metric Home Page


 

 

Dist EA Description

Metric Exception

Expiration

Metric Status

PMCS Target Adv.
PM

PM Phone #
01 3206U1 Storm Damage Repair on Rte 1 0.5 mi N. of Juan Creek Bridge

4/1/97

Exp

7/98
ASHLEY

5385729
03 368401 Yol-80 Mace Blvd OC Reconstruction

6/30/99

Exp

2/98
DREHER,KL

4365973
03 434200 N-A

7/1/97

Exp

11/97
BALOG,SJ

4850349
03 OM59U1 Replace headers on bridge in Yolo Co. on I-5

5/1/97

Exp

-
- -
04 002821 San Mateo Bridge Paint Storage Facility

12/31/98

Exp

06/ 99
HISSEN, R.

5415080
04 004941 Remodel women's restrooms @ SFOBB Maintenance Bldg.

12/31/98

Exp

8/98
HISSEN, R.

5415080
04 012091* SFOBB Demolition
East Spans

12/31/06

-

12/2000
MARONEY, B.

-
04 013091* Carquinez Demolition (1927) span

12/31/06
-

6/2003
CHANG, S. -
04 021921 San Diego-Coronado Abut. 1, Tower & Foundation, Pier 2-23

12/31/00
- - - -
04 04340K* (2-10C) SFOBB East Bay Retrofit Design to P&Q

12/31/00
-

06/ 95
TERPSTRA, K.

5414679
04 0434LK* (20) SFOBB YBI Tunnel

12/31/00
-

11/99
TERPSTRA, K.

5414679
04 04356K* (17) SFOBB WB Suspension Towers

12/31/00
-

5/98
TERPSTRA, K.

5414679
04 0435A1* SFOBB West Approach Seismic Retrofit

12/31/00
-

5/98
TERPSTRA, K.

5414679
04 0435C1* SFOBB TTT Loops, 4th St. onramp, Viaduct Retrofit

12/31/00
-

5/98
TERPSTRA, K.

5414679
04 043821* Richmond-San Rafael Main Span Foundations & Towers

12/31/00
-

3/98
TERPSTRA, K.

5414679
04 043841* Richmond-San Rafael Main Super, Approaches & W Trestle

12/31/00
-

4/98
TERPSTRA, K.

5414679
04 043921* Carquinez WB Facility--RM-1

12/31/00
-

3/97
CHANG, S.

5415146
04 0E0261 Farmers Lane Interchange

12/31/98

Exp

11/99
FAKHARZADEH, S

5416011
04 128991 Pose Webster Radio System (Original Exception for 44010K)

12/31/99

Exp

8/99
HISSEN, R.

5414556
04 133331* (12) SFOBB WB Approach; Main Line

12/31/00
-

6/2000
TERPSTRA, K.

5414679
04 133331* (13) SFOBB WB Approach; Upper Off Ramps

12/31/00
-

6/2000
TERPSTRA, K.

5414679
04 133331* (14) SFOBB WB Approach; TBTB & Harrison

12/31/00
-

6/2000
TERPSTRA, K.

5414679
04 135861 SCR-1 PM 18.2/19.7

6/30/99

Exp

7/99
NG, S. D.

5707326
04 141831 LA-134; Arroyo Seco Br No. 53-0166 - - - - -
04 143511 Seismic Ph 2 - Distribution Structure Br No 33-0061L

12/31/00
-

4/2000
WELSH, M. E.

5415076
04 14670K Seismic Ph2 - Alameda Creek Br No 33-0039

12/31/00
-

3/99
NG, S. D.

5707326
04 148721 (121771 & 148711) Seismic Ph 2 - Walnut Creek OC Br No 28-0258

12/31/00
-

12/99
HISSEN, R.

5415080
04 163221 LA-710; Hobart Yard OH Br. No 53-0840

12/31/00
- - - -
04 171211 LA-002; La Canada Br No. 53-0061; Slide Canyon Br No. 53-0063; Woodwordia Br No. 53-0086 - - - - -
04 174201 Roadway rehab and left-turn channelization on Rte 29 from Mee Lane to Sulphur Creek

12/1/97

Exp

12/98
FAKHARZADEH, S

5416011
04 (18) SFOBB WB Suspension Superstructure

12/31/00
- - - -
04 233971 Construct Soundwall on Hwy 24

12/31/98

Exp

9/98
PANG, P. K.

5415125
04 440111 Pose Webster Stg 1 Seismic (Original Exception for 44010K)

12/31/99

Exp

6/99
GEE, S.

5415295
04 440131 Pose Webster Stg 2 Seismic (Original Exception for 44010K & 440121), Demonstration

9/30/01
-

3/2000
GEE, S.

5414935
04 440141 Pose Webster Stg 2 Seismic (Original Exception for 44010K & 440121

9/30/01
-

4/2001
GEE, S. -
05 019021 Hatton Canyon

12/31/99

Exp

9/2000
J.R. PONCE

6293425
05 444461 Seismic Ph 2 - Huasna River Br No 49-0178

12/31/00
-

4/2000
W.D.O'HALLORAN

6293681
06 019021 05-Mon-1 PM 72.0/75.1

12/31/99

Exp
- - -
06 389301 Tul-63 PM 4.6 Construct Bus Turnout

12/31/98

Exp

11/96
S.A. SHAVER

4253118
07 0N9801 Construct Drainage System Santa Monica Fwy @ 20th/Hoover St. WB On-ramp

3/1/98

Exp
- - -
07 106951 Construct one HOV lane in each dir. on Rte 10 from Baldwin Ave. to Rte 605

9/30/00
-

7/2000
HUANG, D

6477195
07 107201 Borchard Road Interchange Mod., VEN-101 PM 6.6/7.4

12/31/00
-

3/2000
VELASQUEZ, T

6478083
07 117361 West end approach span travellers on Rte 47 @ Vincent Thomas Bridge

2/1/97
Exp

05/ /97
ALAMEDDINE, E

6470141
07 1194A1 LA-105 PM R9.6/R10.0 Imperial Hwy at Willmington; Construct Hwy Grade Sep. (Phase2)

12/31/00
-

11/99
ALY, E

6470694
07 119851 HOV Lane ea. dir. LA-405 PM 21.3/26.0

12/31/99

Exp

5/2001
NOVOTNY, S

6474289
07 122401 Construct HOV lane in each dir. on Rte 10 from Rte 57 to San Bernardino Co. Li ne

12/31/99

Exp

9/2000
PALAHA, J

6476926
07 128400 Henry Ford Avenue RR Grade Separation - -

10/99
KOPPARAM, V

6475581
07 131011 TCM Building 12/31/00 -

10/2000
BUHA, D

6477285
07 138201 Seismic Ph 2 - Schuyler Heim Br No 56-2618 12/31/00 -

3/99
NOVOTNY, S

6474289
07 139901 LA-101 PM 10.3/11.0

12/31/99

Exp

5/1/2001
WONG, R

6476010
07 1N0801 Repair/Landscape City street island @ 23rd & Figueroa

6/30/98

Exp

-
SHETH, O

6478595
08 268311 SBd-138 PM T16.3/19.7

12/31/99

Exp

12/99
MORHIG, G.

6707165
08 322001 SBD-10 PM 8.5/9.6

12/31/98

Exp

4/99
RAZA, S.

6705953
08 340801 SBd-10 PM 15.3/17.0

9/30/00
-

8/2000
RAZA, S.

6704960
08 354301 RIV-215 PM R18.3/R18.7; O/C widening and ramp modificiation at Newport Rd.

9/30/00
-

5/2000
SHIEH, C.

6707189
08 371301 Seismic Ph 2 - Colton I/C Br No 54-0471, 54-1064F and 54-0823G

12/31/00
-

5/2000
RAZA, S.

6704960
09 251201 Iny-395 PM 41.4/45.6

12/31/98

Exp

12/98
C.L. HAACK

4224338
09 262301 Construct diversion channel E. of Rte 395 1.1 mi N. of Sage Flat Rd.

12/1/97

Exp

12/97
D.GRAH

6270734
09 346911 Add passing lanes in both directions on Rte 395 from Princess Pat Mine Rd. to Proper Dr.

4/1/97

Exp
- - -
10 438441 Planting for environmental mitigation on Route 37 near Napa River Bridge

1/20/98

Exp
- - -
10 495401 Repair Bridge near Los Banos @ Rte 5/152 separation

4/1/97

Exp

1/2000
C. ADAMS

4237300
11 010101 Planting on Rte 52 from Rte 15 to 3.0 mi E. of Santo Rd.

2/1/97

Exp

TB/ /
HAM, TOM

6886719
11 010731 SD-125 19.8/21.3 Sales Tax

6/30/00
-

6/2000
HULL, JOE

6883633
11 021931* SD-Coronado Tower & Foundation, Pier 24-32

12/31/00
-

4/98
ORSO-DELGADO

6886803
11 021941* San Diego-Coronado East Approach Ramps

12/31/00

-

4/98
ORSO-DELGADO

6886803
11 030171 Construct NB Aux lanes, direct connector, widen, and grade for ultimate on Rte 5 & Rte 805

11/1/96

Exp

12/2000
ALLISON, TIM

6886728
11 030191 Construct NB and SB HOV lanes on Rte 5 from Rte 805 to 0.3 mi N. of Del Mar Heights Rd. - -

2/98
ALLISON, TIM

6886728
12 071801 Establish existing planting on Rte 5 from Alton Pkwy to Redhill Ave.

4/1/97

Exp
- - -

Return to Top

Return to Metric Home Page