04 - 043634 WEST APPROACH



JULY 29, 1999







PROJECT CONTACT PERSONS
PROJECT MANAGERHelena "Lenka" Culik-Caro(510) 286 - 5759
PUBLIC AFFAIRS OFFICEAnne Tobias(415) 989-1446 (EXT. 12)
PUBLIC INFORMATION OFFICEGreg Bayol(510) 286 - 4444
CONTRACTORDillingham Construction NA INC.(510) 463 - 3300

CONTRACT INFORMATION
CONTRACTOR'S BID$2,675,624
NUMBER OF WORKING DAYS250
CONTRACT AWARDEDJuly 9, 1997
DATE COMPLETEDSept. 28, 1998



PROJECT SCOPE HIGHLIGHTS

The West Approach connects the roadway located on ground level with the High Rise over the water. It is approximately 220 feet long, and is located entirely above dry land. The seismic retrofit of the West Approach will entail: