Note: This list is not updated when addenda are issued. For informational purposes only.
Contract Number 04-4A8204
Date Adv.: 06/23/2014

Item No.Item
Code
Item Description Unit of
Measure
Estimated
Quantity
1070030LEAD COMPLIANCE PLANLSLUMP SUM
2120090CONSTRUCTION AREA SIGNSLSLUMP SUM
3120100TRAFFIC CONTROL SYSTEMLSLUMP SUM
4128651PORTABLE CHANGEABLE MESSAGE SIGN (EA)EA1
5129000TEMPORARY RAILING (TYPE K)LF720
6129150TEMPORARY TRAFFIC SCREENLF720
7130100JOB SITE MANAGEMENTLSLUMP SUM
8130200PREPARE WATER POLLUTION CONTROL PROGRAMLSLUMP SUM
9130570TEMPORARY COVERSQYD500
10130610TEMPORARY CHECK DAMLF30
11130620TEMPORARY DRAINAGE INLET PROTECTIONEA3
12130710TEMPORARY CONSTRUCTION ENTRANCEEA2
13130730STREET SWEEPINGLSLUMP SUM
14130900TEMPORARY CONCRETE WASHOUTLSLUMP SUM
15141000TEMPORARY FENCE (TYPE ESA)LF65
16153121REMOVE CONCRETE (CY)CY2
17160102CLEARING AND GRUBBING (LS)LSLUMP SUM
18190105ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD)CY270
19200002ROADSIDE CLEARINGLSLUMP SUM
20200122WEED GERMINATIONSQYD1,040
21200123CULTIVATIONSQYD1,040
22202037ORGANIC FERTILIZERLB56
23204045SODSQYD1,040
24204099PLANT ESTABLISHMENT WORKLSLUMP SUM
25210110IMPORTED TOPSOIL (CY)CY220
26210350FIBER ROLLSLF880
27210600COMPOSTSQFT9,400
28210630INCORPORATE MATERIALSSQFT9,400
29731509MINOR CONCRETE (CONCRETE MOW STRIP)CY25
30860090MAINTAINING EXISTING TRAFFIC MANAGEMENT SYSTEM ELEMENTS DURING CONSTRUCTIONLSLUMP SUM
31999990MOBILIZATIONLSLUMP SUM