Submit new inquiry for this projectInquiry #1: Construction water access? I didn't notice any existing irrigation on the plans, is there any source for construction water onsite or is it offsite of the project?
Inquiry submitted 01/30/2013
Response #1:Water source is found at the toll plaza, a back flow preventer.
Response posted 02/04/2013
Inquiry #2: Do we need to include money in our bid for all the tolls of our workers, vendors, subcontractors and personnel that will be required to visit the site on a daily basis or is there an alternative option?
Inquiry submitted 02/05/2013
Response #1:Toll fees are paid by the Contractor.
Response posted 02/07/2013
Inquiry #3: Item 22 - EROSION CONTROL (COMPOST BLANKET) does not look to have a spec in the special provisions or plan sheets. specific materials of compost and application/construction is needed for this line item. Please advise. Thank you.
Inquiry submitted 02/06/2013
Response #1:Bid as you see it.
Response posted 02/07/2013
Inquiry #4: Please verify the rates of germination of the seed mix. Suppliers are saying it is completely incorrect.
Inquiry submitted 02/06/2013
Response #1:Bid as you see it.
Response posted 02/07/2013
The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.