Inquiry #1: Will you be providing Cross-Section for this project? Also, will you be proving the .dgn files of the Cross-Sections?
Inquiry submitted 07/17/2012

Response #1: Cross sections are now available as stated in Section 2-1.03B "Supplemental Project Information" of the amended Standard Specifications, at: http://www.dot.ca.gov/hq/esc/oe/project_ads_addenda/10/10-0E6134/pdf/
Response posted 07/17/2012




Inquiry #2: Pile quantities on sheet 607 show 90 each of Class 200 (Alt x) and 54 each of Class 140 (Alt X). Plan sheet 608 in the pile data table shows Class 200 at bent 2 which should be 54 each and Class 140 at both abutments which should be 90 each. Please clarify.
Inquiry submitted 08/23/2012

Response #1: Submitted
Response posted 08/24/2012


Response #2: Please refer to Addendum No. 1 dated August 27, 2012.
Response posted 08/29/2012




Inquiry #3: The earthwork quantities summary on Sheet Q-1 of the plans shows a deduction of 20% from the roadway excavation quantities for "unsuitable material". There are no other references in the plans or specifications giving any location or characterization of this unsuitable material. As it will significantly affect the roadway excavation and import borrow quantities please clarify where this material is on the project, what phase of work will it affect and how the contractor is to be paid for dealing with it.
Inquiry submitted 08/31/2012

Response #1: Submitted
Response posted 09/04/2012


Response #2: Refer to Addendum No. 2, dated September 7, 2012.
Response posted 09/07/2012




Inquiry #4: The specifications for this project have not given any indicaton of the Caltrans allowance for subsidence and/or the grading factor to be used in the calculation of the required import borrow. Please provide this information for the contractor's use.
Inquiry submitted 08/31/2012

Response #1: Submitted
Response posted 09/04/2012


Response #2: Please bid per contract.
Response posted 09/07/2012




Inquiry #5: Plan sheet 613 shows two vaults at abutment 1. Plan sheet 614 shows one vault at abutment 3. Quantities of 20" casing and 12" ductile iron pipe appear to be adequate for water line and future openings. Please clarify if there is anything running through the extra vault at abutment 1.
Inquiry submitted 08/31/2012

Response #1: Submitted
Response posted 09/04/2012


Response #2: Please bid per contract plans.
Response posted 09/05/2012




Inquiry #6: The Earthwork Quantities Summary on Sheet Q-1, shows the stockpile area as having 42,282 CY of Exc. The Contour Grading sheet G-3, shows the stock pile area as having an existing max elevation of 64. Yet when we looked at the jobsite, the stockpile is not there, and the existing elevation is at the same grade as the highway. Will the Stockpile dirt be present before the job is to begin, or should this quantity be removed from the total. Please clarify
Inquiry submitted 09/04/2012

Response #1: Submitted
Response posted 09/04/2012


Response #2: The referenced stockpile is generated from excavation taking place in Phase 1 contract 10-0E6114, and will be present before this contract (10-0E6134) is to begin. Therefore, the quantity of roadway excavation shown for this stockpile on Summary of Quantities Q-1 (sheet 407 of the plans) should remain.
Response posted 09/05/2012




Inquiry #7: The project "Amendments to Standard Specifications" added section 6-1.085 Buy America. I do not see a Federal aid number within the specifications.

Please confirm that this project is NOT subject to the "Buy America" material requirement for steel products.

Inquiry submitted 09/04/2012

Response #1: Submitted
Response posted 09/04/2012


Response #2: This is not a Federal Aid project, therefore, the requirements of Section 6-1.085 "BUY AMERICA (23 CFR 635.410)" of the amended Standard Specifications, for steel and iron products, do not apply to this contract. However, Section 6-1.087 "BUY AMERICA (PUB RES CODE § 42703(d))," for crumb rubber, does apply to this contract.
Response posted 09/07/2012




Inquiry #8: Sheet L-8 is calling out one (1)chain link gate (Type CL-6). Sheet L-6 is calling out three (3) chain link gates (Type CL-6). Sheet L-10 is calling out one (1) chain link gate (Type CL-6). Sheet L-17 is calling out one (1) chain link Gate (Type CL-6).
None of these sheets include gate widths, nor does the Bid Item List include a Bid Item for these gates.

Please provide a bid number with gate widths for the chain link gates (Type CL-6).

Inquiry submitted 09/04/2012

Response #1: Submitted
Response posted 09/05/2012


Response #2:The Chain Link Fence Gates are required as depicted in the Layout Plan Sheets. Contractor is to bid per the current contract documents.
Response posted 09/11/2012




Inquiry #9: Sheet DD-9 (Drainage System No. 32) shows Cable Railing on HW1 & HW2 for a total of 144 LF.

The Bid Item List does not include a bid number for the Cable Railing. Please provide a Bid Number for the Cable Railing shown on DD-9.

Inquiry submitted 09/04/2012

Response #1: Submitted
Response posted 09/05/2012


Response #2:Cable Railing as shown DD-9 is required. Contractor is to bid per the current contract documents.
Response posted 09/11/2012




Inquiry #10: Will Caltrans have the existing buildings and structures with in the project limits removed in their entirety before the start of the project? If not what item of work is this to be paid under?
Inquiry submitted 09/05/2012

Response #1: Submitted
Response posted 09/06/2012


Response #2: Yes, the existing buildings within the project limits will be removed by others prior to the start of construction.
Response posted 09/06/2012


Response #3: Refer to Addendum No. 2, dated September 7, 2012.
Response posted 09/07/2012




Inquiry #11: Will the SCADA system for the Drainage pumping equipment for the city of Manteca be paid in bid item 156?
Inquiry submitted 09/05/2012

Response #1: Submitted
Response posted 09/06/2012


Response #2: Yes, refer to Section 10-4.03 "DRAINAGE PUMPING EQUIPMENT - CITY OF MANTECA," subsection "MEASUREMENT AND PAYMENT," of the Special Provisions.
Response posted 09/06/2012




Inquiry #12: The plans & specifications for the project do not address the demolition & removal of the numerous existing buildings and structures which conflict with the new construction. There is no indication that they are to be removed by others or by this contractor and there are no preliminary environmental reports for possible asbestos abatement. Please clarify.
Inquiry submitted 09/05/2012

Response #1: Submitted
Response posted 09/06/2012


Response #2: Refer to the response to Inquiry #10.
Response posted 09/06/2012




Inquiry #13: Several outstanding critical questions have not yet been answered; with less than a week remaining till bid opening. Due to the significant impact these questions have on the final bid, we respectfully request the bid date be moved back a week or two.
Inquiry submitted 09/06/2012

Response #1: Submitted
Response posted 09/06/2012


Response #2:The Bid Opening Date is tomorrow and an Addendum will not be issued. Contractor to bid per the current contract bid documents.
Response posted 09/11/2012




Inquiry #14: As there are still several questions that have not yet been answered, we are requesting an extention of the bid due date.
Inquiry submitted 09/07/2012

Response #1: Submitted
Response posted 09/07/2012


Response #2:The Bid Opening Date is tomorrow and an Addendum will not be issued. Contractor to bid per the current contract bid documents.
Response posted 09/11/2012




Inquiry #15: Note # 131 on page E-3 states per drawing No. ST-27 and ST-28 on sheet E-49. These drawings do not exist. Also Note # 180 on Sheet E-3 states per Drawing No. R-32 on sheet E-50, this also does not exist. Please supply drawings required for these poles.
Inquiry submitted 09/07/2012

Response #1: Submitted
Response posted 09/07/2012


Response #2: Please bid per contract.
Response posted 09/07/2012




Inquiry #16: Addendum 1 changed the working days from 430 to 300. The project did not change in scope, why is it the days decreased so significantly? The project already is very difficult to build in the original time allowed. Now the project has been decreased by 130 days this will almost certainly add cost to the project if it can even be accomplished. Please clarify?
Inquiry submitted 09/07/2012

Response #1: Submitted
Response posted 09/07/2012


Response #2:No additional information will be provided. Refer to Section 2-1.12B, "Bid Item List and Bid Comparison," of the amended Standard Specifications: "Submit a bid based on the work item quantities the Department shows in the Bid Item List".
Response posted 09/11/2012




Inquiry #17: Addendum 2 changed the Roadway Excavation quantity from 185,000 cy to 231,000 cy put did not change the imported borrow quantity why?
Inquiry submitted 09/07/2012

Response #1: Submitted
Response posted 09/07/2012


Response #2:No additional information will be provided. Refer to Section 2-1.12B, "Bid Item List and Bid Comparison," of the amended Standard Specifications: "Submit a bid based on the work item quantities the Department shows in the Bid Item List".
Response posted 09/11/2012




Inquiry #18: Please post the Mandatory Pre-bid meeting Contractor's attendees.
Inquiry submitted 09/09/2012

Response #1:Submitted for consideration.
Response posted 09/10/2012


Response #2:Contractor's in attendence for the Mandatory Pre-bid were the following:
Teichert Construction - 209-321-1503
CC Myers, Inc - 916-635-9370
RGW Construction - 925-606-2440
Granite Constr.- 916-855-4400, 209-982-4750
Road and Highway Builders of CA - 916-649-4504
Desilva Gates Construction - 925-596-3607
Disney Construction - 650-259-9545
George Reed, Inc - 209-523-0734
Diablo Contractors, Inc - 925-552-8250
R & L Brosamer, Inc - 510-772-0498, 925-627-1700
Flatiron - 707-742-6000

Response posted 09/11/2012




Inquiry #19: Plan sheets L-13 & 19 refer to "DTBB connection to Concrete Barrier" between the Barriers and Alternative Crash Cushions. Quantity sheet Q-3 contains a chart for Double Thrie Beam Barrier which quantifies these locations. The DTBB Connection is a (N) no-pay Item. However, thereis no Item for Double Thrie Beam Barrier, and thus no method of payment for these connections. Please provide a Bid Item.
Inquiry submitted 09/10/2012

Response #1:Submitted for consideration.
Response posted 09/10/2012


Response #2:The L-13, L-19, Q-3 reference to DTBB is a typograhical error. The intend of the design is to provide a permanent end treatment system (CAT or approved alternative) connecting to the proposed concrete barrier. The connection from the end treatment to the concrete barrier is to be paid under the contract item for ALTERNATIVE CRASH CUSHION.
Response posted 09/12/2012




Inquiry #20: This project is scheduled to bid tomorrow 9/12/2012 and we barely received answers to our questions today. It is virtually impossible to recieve new supplier pricing or have our supplier's revise pricing by tomorrow.

We are, once again, requesting a bid date change.

Inquiry submitted 09/11/2012

Response #1:The Bid Openging Date is tomorrow and an Addendum will not be issued. Contractor to bid per the current contract bid documents.
Response posted 09/11/2012






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.