Caltrans Office Engineer

Viewing inquiries for 08-0N1204

Submit new inquiry for this project


Inquiry #1: The plans, specs and addenda available online for this project appear to be incorrect. They have 2010 advertisement and bid dates on them and the list of quantities does not match the project description or those shown in the list of bid items.
Inquiry submitted 02/04/2013

Response #1:Submitted for consideration
Response posted 02/05/2013


Response #2:It appears that you are viewing the prior advertisement of this project. The project has been re-advertised as an overlay and not slurry seal.
Response posted 02/07/2013




Inquiry #2: Regarding Page 52 Item 2.10

Question- Is the 7.0 percent referenced in Item 2.10 indicate 7.0 percent based on dry weight of aggregate or 7.0 percent based on total weight of mix?

Inquiry submitted 02/27/2013

Response #1:Submitted for consideration
Response posted 03/01/2013


Response #2:This project is still using the 2006 specs so the percentage is based on the weight of the dry aggregate.
Response posted 03/08/2013






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.