Caltrans Office Engineer

Viewing inquiries for 07-285004

Submit new inquiry for this project


Inquiry #1: Reference Plan Sheet No. 2, L-1:Metal Beam Guard Railing-
At Station 60+25, an End Anchor Assembly (Type SFT) is indicated. There is no Pay Item, what is the Method of Payment for the End Anchor Assembly (Type SFT)?

Inquiry submitted 10/29/2012

Response #1:Please Bid as you see it.
Response posted 10/29/2012






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.