Viewing inquiries for 05-0Q6204
Submit new inquiry for this projectInquiry #1: Does Caltrans intend the contractor to dispose of all the Type Y-1 Aerially Deposited Lead at the area between NBLOL1 Sta 102+00 and 110+00 and the NB Los Berros On Ramp, as shown on plan sheet C-3?
Inquiry submitted 06/21/2012
Response #1:Submitted for consideration.
Response posted 06/21/2012
Response #2:Yes, Reference Special Provision, Section 5-1.13 and Section 10-1.26 and in accordance with contract plans C-3.
Response posted 06/22/2012
Inquiry #2: Under what bid item(s) will Caltrans pay for the removal of the existing downdrains?
Inquiry submitted 06/21/2012
Response #1:Submitted for consideration.
Response posted 06/22/2012
Response #2:Caltrans will pay for removal of existing down drains under Item 26, Roadway Excavation. Down drains are within the roadway prism. Reference Standard Specification section 19-1.01 and section 19-1.04.
Response posted 06/25/2012
Inquiry #3: Under what bid item(s) will Caltrans pay for the removal of existing AC Dike?
Inquiry submitted 06/22/2012
Response #1:Submittted for consideration.
Response posted 06/22/2012
Response #2:AC Dike removal will be paid for under Item 26, Roadway Excavation.
Response posted 06/26/2012
Inquiry #4: For Bid Item #34 Lean Concrete Base, the actual quantity appears to be about 115 CY, instead of 300 CY? Please verify bid quantity.
Inquiry submitted 06/25/2012
Response #1:Submitted for consideration.
Response posted 06/25/2012
Response #2:Please bid it according to contract plans and specifications.
Response posted 06/27/2012
The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.