Inquiry #1: Dear sir I would like to Know the liquidated damage amount and the SBE Amount
Thank you, Guy Piombo

Inquiry submitted 05/03/2013

Response #1:See Section 8-1.10 LIQUIDATED DAMAGES of the 2010 Standard Specifications.
Response posted 05/08/2013






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.