Viewing inquiries for 04-3A3304

Submit new inquiry for this project


Inquiry #1: Please consider moving the bid date two weeks. Thanks
Inquiry submitted 10/01/2012

Response #1:Submitted for consideration.
Response posted 10/02/2012


Response #2:Request noted.
Response posted 10/08/2012


Response #3:Addendum 1 changed the bid date from Oct.9 to Oct. 24, 2012. See Addendum 1.
Response posted 10/09/2012




Inquiry #2: Duty Senior;

Project plans for the above referenced project do not include demolition plans. There are several large oak trees adjacent to the widening/ shoulder work which appear to conflict with the work, but are not noted to be removed. Can you provide a list of trees which need to be removed for this project? Also, the work appears to encroach on existing vineyards, the extent of which is not clear on the plans. Is the clearing and related irrigation removal a part of this contract? If so, can you issue a plan showing the extent of vineyard removal and also any related irrigation systems that need to be removed?

Inquiry submitted 10/03/2012

Response #1:Submitted for consideration.
Response posted 10/04/2012


Response #2:There are a total of 7 trees in conflicts with the widening work. These trees will be removed by others before the construction starts. The layout sheets already showed the new right of way lines. The contractor needs to contact Caltrans Right of Way Engineering for accurate right of way data. The vinery and the irrigation system that encroach into the new right of lines shall be removed by the contractor under the pay item "CLEARING AND GRUBBING".
Response posted 10/08/2012


Response #3:The layout sheets already showed the new right of way lines. The contractor needs to contact Caltrans Right of Way Engineering for accurate right of way data. The trees in conflicts (7 trees in total) with the widening shall be removed by contractor under the pay item "CLEARING AND GRUBBING". The vinery and the irrigation system that encroach into the new right of lines shall be removed by the contractor under the same pay item.
Response posted 10/08/2012




Inquiry #3: Duty Senior,

Are there cross sections available for the project 04-3A3304?

Inquiry submitted 10/03/2012

Response #1:Submitted for consideration.
Response posted 10/04/2012


Response #2:Download below:



www.dot.ca.gov/dist4/construction/contracts/04-3A3304/XSections_pdf.zip (zipped pdf, 16.1MB)
Response posted 10/22/2012




Inquiry #4: Why have you not answered Inquiry #3? This was posted on 10/03/2012.
Please provide Cross Sections for accurate bidding purposes.

Inquiry submitted 10/22/2012

Response #1:Cross sections are now posted for BI#3.
Response posted 10/22/2012






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.