Inquiry #1: Are cross sections available for this project?
Inquiry submitted 10/17/2012

Response #1:Cross sections can be downloaded below:


www.dot.ca.gov/dist4/construction/contracts/04-1G2404/XSections.pdf(pdf, 3.6MB)
Response posted 10/18/2012




Inquiry #2: How will the contractor be paid for the Biological Monitoring on this particular project?
Inquiry submitted 10/29/2012

Response #1:Submitted for consideration.
Response posted 10/30/2012






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.