Caltrans Office Engineer

Viewing inquiries for 03-3F4204

Submit new inquiry for this project


Inquiry #1: We are having trouble finding the Hours of work for this project? Please advise.
Inquiry submitted 03/21/2013

Response #1:3/22/13: Please Refer to Section 12 Temporary Traffic Control of the Special Provisions. Furthermore, please refer to the lane closure charts on page 12 of the contract documents.
Response posted 03/22/2013






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.