Inquiry #1: Item Number 15 appears to be overstated,
Inquiry submitted 12/06/2012

Response #1:12/6/12: Your inquiry has been received and is being reviewed. Thank you for your patience.
Response posted 12/06/2012


Response #2: 12/7/12: Your question is under review. An addendum is under consideration. Unless an addendum is issued addressing your concern, please bid per the current contract documents.
Response posted 12/07/2012


Response #3: 12/7/12: Please refer to Addendum Number 1 dated December 7, 2012.
Response posted 12/07/2012






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.