Viewing inquiries for 08-449104

Submit new inquiry for this project


Inquiry #1: Our review of the Colorado River Basin Regional Water Quality Control Board Order issued May 14, 2013 and the California Department of Fish and Wildlife Streambed Alteratin Agreement signed on June 6 and Jun 10, 2013 disclose a substantial difference in the stated location of the area addressed by these docuements. The former document describes the location as in Section 21, Township 7 south, Range 9 east; while the latter document describes the location as Section 28, Township 8 south, Range 11 east. This difference is substantial,approximately 14 miles, and could arise at a crucial time in the prosecution of the project and result in serious delays. We raise this issue in the best interests of the project, considering the delicate nature of the environmental issues in this area of pristine natural beauty.
Inquiry submitted 09/12/2013

Response #1:Submitted for consideration.


Response posted 09/12/2013


Response #2:Submitted for consideration.


Response posted 09/16/2013


Response #3:The Colorado River Basin RWQCB 401 Order issued May 14, 2013 on page 7 under Location is incorrect. It is being revised by them. The Right of Way Record map (attached) properly shows the project location within Section 28, T8S, R11E of the San Bernardino Base & Meridian. Bidders can be notified of this error being corrected.
Response posted 09/30/2013




Inquiry #2: Special Provision 2-1.06B indicates cross sections are available. Can these be added to the information handout and be provided to the contractor in electronic format.
Inquiry submitted 09/17/2013

Response #1:Submitted for consideration.

Response posted 09/18/2013


Response #2:Cross-Sections files for this project are advertised electronicly with the information handout. Please look it up online.
Response posted 09/23/2013




Inquiry #3: Will Permanent Steel Deck Forms be allowed for deck construction
Inquiry submitted 09/25/2013

Response #1:Submitted for consideration
Response posted 09/26/2013


Response #2:Please refer to Addendum # 1 issued on October 01, 2013.
Response posted 10/01/2013






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.