Inquiry #1: Reference Notice to Bidders page 1 of the Special Provisions, paragraph 16 regarding the Mandatory Prebid Meeting to be held on Thursday, June 5, 2014. We would like to request that the date of the prebid meeting be changed to any day but Thursday as this is typically "bid day" for Caltrans projects in Southern California (in fact there are currently two bids scheduled for that day). Friday, June 6 would work well for the prebid meeting.
Inquiry submitted 05/15/2014

Response #1:Submitted for consideration.
Response posted 05/15/2014


Response #2:The mandatory prebid meeting will be held as scheduled. Concerns regarding Thursday meetings are duly noted.

Response posted 05/15/2014




Inquiry #2: The dimensioning for the monument sign/structures on plan sheets 199-201 appears to be greatly overstated. Could Caltrans please review and provide proper dimensioning?
Inquiry submitted 05/27/2014

Response #1:An addendum will be issued to provide the proper dimensioning.
Response posted 05/27/2014




Inquiry #3: Are cross sections available for this project? If they are available, how can we secure a set?
Inquiry submitted 05/27/2014

Response #1:Information is available on line in the project supplemental information folder.
No Action Required.
Response posted 05/27/2014




Inquiry #4: In reviewing the special provisions and the information handout documents, I could not locate the soils report for this project. Is the soils report and or boring logs available for this project?
Inquiry submitted 05/28/2014

Response #1:Submitted for consideration.
Response posted 05/28/2014


Response #2:Log of test borings included in project plans.
Response posted 05/29/2014




Inquiry #5: Reference Bid Item 115(F) (Structural Concrete, Wall) and Plan Sheet DD-15. Please review Bid Quantity, as we have come up with a substantial amount more than the Engineer's Quantity.
Inquiry submitted 06/02/2014

Response #1:Submitted for consideration.
Response posted 06/02/2014


Response #2:Quantity for Bid item 115(F) is as shown. Bid per current contract documents.
Response posted 06/06/2014




Inquiry #6: Reference Drainage Quantities sheets. Some Headwalls (example; 102a) contains payment in both the Minor Concrete, Minor Structure Item (121F), as well as the Structural Concrete, Wall Item (115F). Can you please verify what is covered in each of these items for these specific walls?
Inquiry submitted 06/02/2014

Response #1:Submitted for consideration.
Response posted 06/02/2014


Response #2:Structural Concrete(Wall) is in reference to Wing wall, its footing and cutoff wall.

Minor Concrete (Minor Structure) is in reference to Head walls.

Response posted 06/06/2014




Inquiry #7: A good number of headwalls do not provide a Caltrans standard for construction (example; 64d). What standard is applicable for the headwalls that do not call out a standard?
Inquiry submitted 06/02/2014

Response #1:Submitted for consideration.
Response posted 06/02/2014


Response #2:Please refer to Caltrans standard plans D89 for straight and L type Head Walls. Bid per current contract documents.
Response posted 06/04/2014




Inquiry #8: Reference Mod. Parkway Details on Sheet DD-18. The Plan View detail shows "Splash Walls" and references DD-19 for a detail, but DD-19 does not contain such a detail. Please provide.
Inquiry submitted 06/03/2014

Response #1:Submitted for consideration.
Response posted 06/03/2014


Response #2:An Addendum will be forthcoming to address this issue
Response posted 06/06/2014




Inquiry #9: In the pre-bid presentation this morning, and in a subsequent conversation afterwards, Jason Bennecke said that this being a local agency AAA project that the Caltrans Engineer utilizing the Fontana Lab, would be responsible for all inspection and testing required for soils, concrete, asphalt, masonry, steel, welding etc. It was communicated that the Prime Contractor did not have any QC responsibilities in their scope. In reviewing the Special Provisions for this project, it is stated throughout that the Prime is to "provide a testing laboratory to perform quality control tests" (Sect. 28-2.01D(4), "submit the name of your proposed testing laboratory" (28-2.01C(1,"employ a special inspector and an authorized laboratory" (Sect 58). These are only a few examples.

Please clarify if the Prime will be responsible to subcontract with a Caltrans Certified inspection and testing firm as indicated in the Special Provisions.

Inquiry submitted 06/05/2014

Response #1:Submitted for consideration.
Response posted 06/05/2014


Response #2:Responsibility for testing is as stated in the Notice To Bidders and Special Provisions for the contract. Bid per current contract documents.

Response posted 06/11/2014




Inquiry #10: Please confirm that the Jacked 24" RCP (DS 149f) is to be paid in Bid Item # 142.
Inquiry submitted 06/05/2014

Response #1:Submitted for consideration.
Response posted 06/05/2014


Response #2:An Addendum will be released for clarification.
Response posted 06/10/2014




Inquiry #11: There does not seem to be any 48" RCP on the Drainage plans, but Bid Item # 145 shows 320 LF. Please review and advise.
Inquiry submitted 06/05/2014

Response #1:Submitted for consideration.
Response posted 06/05/2014


Response #2: Please see plan sheets D-11 and DQ-31. Bid per current contract documents
Response posted 06/09/2014




Inquiry #12: Is it the intent to put STEEL Flared End Sections on the end of RCP? All of the FES's are called to be Steel. Please advise
Inquiry submitted 06/05/2014

Response #1:Submitted for consideration.
Response posted 06/05/2014


Response #2:Yes, Flared End Sections are steel as indicated. Bid per current contract document.

Response posted 06/11/2014




Inquiry #13: We would like to request a copy of the sign in sheet of all who attended the mandatory pre-bid meeting held on June 5, 2104.
Inquiry submitted 06/06/2014

Response #1:Submitted for consideration.
Response posted 06/09/2014


Response #2:Copies of the sign-in sheets for Primes and Subs who attended the mandatory meeting for project # 08-3401U4 on June 5,2014 are available.
To obtain a copy by email, Please send a request email to:
d8.pbi@dot.ca.gov and the sign-in sheets will be sent back to you. Thanks.
Response posted 06/09/2014




Inquiry #14: Item 61 Cold Plane AC Pvmnt is bid by the SQYD. There are 2 different sections to be cold planed .15' & .25' thick. Could you please separate these quantities so the quoted unit will be accurate?
Inquiry submitted 06/06/2014

Response #1:Submitted for consideration.
Response posted 06/09/2014


Response #2:Bid per current contract documents.

Response posted 06/09/2014




Inquiry #15: Reference Special Provisions Page 39-Section 14-6.02C(5), paragraph beginning with "within Cajon Creek Bridge Area...". Item No. 1 states the "Bat Houses must be constructed...". Please provide a detail and quantity of Bat Houses that are required. Also, where will the cost of the Bat Houses be paid?
Inquiry submitted 06/09/2014

Response #1:Submitted for consideration.
Response posted 06/09/2014


Response #2:An addendum will be issued to provide information in regards to "Bat Houses". The cost is covered under section 9-1.03 of Standard Specification 2010.
Response posted 07/17/2014




Inquiry #16: Reference Special Provisions Page 42 - Section 14-6.07 and Page 44 - Section 14-6.08. Both of these sections indicate "not used" under their payment sections. Where is the cost to comply with these sections to be paid? Will bid items be added to cover these requirments?
Inquiry submitted 06/09/2014

Response #1:Submitted for consideration.
Response posted 06/09/2014


Response #2:Please see section 9-1.03 PAYMENT SCOPE of the STANDARD SPECIFICATIONS 2010. Bid per current contract documents.

Response posted 06/09/2014




Inquiry #17: Reference the "California Department of Fish and Wildlife" permit provided in the Information Handout, page 4 of 11, item 2.2 - Temporary Fencing. This paragraph states that the "permittee shall install temporary desert tortoise exclusionary fencing...." if the pre-construction surveys indicate the presence of desert tortoise on the project site. We assume that because there is no bid item for temporary desert tortoise fence, this will be paid for as extra work if required. Please confirm.
Inquiry submitted 06/09/2014

Response #1:Submitted for consideration.
Response posted 06/09/2014


Response #2:Please bid per current contract documents.

Response posted 06/11/2014




Inquiry #18: Where is the work for item 188-Concrete Barrier (Type K) shown?
Inquiry submitted 06/09/2014

Response #1:Submitted for consideration.
Response posted 06/09/2014


Response #2:See Stage Construction Plans. Bid per current contract documents.


Response posted 06/11/2014


Response #3:Please note this inquiry has been updated. An addendum will be issued to delete item.
Response posted 07/16/2014




Inquiry #19: It is our understanding that column 2 and 3 of the sub listing form must be submitted within 24 hours of the bid opening. With the bid date of July 3, this would make the form due by 2:00 pm on July 4 which is a designated holiday. We would like to request that the bid date be postponed a minimum of 1 week so that contractors are not having to work on the July 4th holiday in order to get the sublisting form submitted.
Inquiry submitted 06/10/2014

Response #1:Submitted for consideration.
Response posted 06/10/2014


Response #2:Bid opening is as scheduled. Per GC 6707.
When the last day for filing any instrument or other document with a state agency falls upon a Saturday or holiday, such act may be performed upon the next business day with the same effect as if it had been performed upon the day appointed.

Response posted 06/17/2014




Inquiry #20: Our estimated quantity for Item 169-Minor Concrete (Gutter)(43 cy)is substantially less than the Engineer's Estimate of 256 cy. Please review
Inquiry submitted 06/10/2014

Response #1:Submitted for consideration.
Response posted 06/10/2014


Response #2: An addendum will be issued to revise the quantity.

Response posted 06/11/2014




Inquiry #21: Re: 08-3401U4 Section 19-4 Rock Excavation Controlled Blasting

Q - Is pre-splitting the only method of Controlled Blasting that will be acceptable or can step drilling be utilized for the 2:1 slope described on Plan sheets C-62, C-63, and L-42?

Inquiry submitted 06/11/2014

Response #1:Submitted for consideration.
Response posted 06/11/2014


Response #2:Bid per current contract documents.

Response posted 06/19/2014




Inquiry #22: The "Remove Concrete Quantity" column seems overstated on sheet no.785 (Q-19). Please review and clarify your take-off quantity for cross-gutter removal on sheet no. C-28 from sta. 503+62.32 to sta. 505+23.99 Rt. It appears that there is a magnitude bust between "square yards" vs. "square feet" of removals.
Inquiry submitted 06/11/2014

Response #1:Submitted for consideration.

Response posted 06/11/2014


Response #2:An addendum will be issued to revise the quantity.

Response posted 06/19/2014




Inquiry #23: It appears that the quantity for Item 76-Rock Excavation, 37,500 cy, is also included with the quantity for Item 75-Roadway Excavation, 394,000 cy. Will rock excavation be measured and paid for in both items?
Inquiry submitted 06/11/2014

Response #1:Submitted for consideration.

Response posted 06/11/2014


Response #2:Bid per current contract documents.

Response posted 06/19/2014




Inquiry #24: Please review Engineer's Quantity for Bid Item # 120 (Struct. Concrete, Box Culvert), specifically DS 113b/c and DS 134c. The quantities seem to be overstated.
Inquiry submitted 06/12/2014

Response #1:Submitted for consideration.

Response posted 06/13/2014


Response #2:Please bid per current contract documents.

Response posted 06/16/2014




Inquiry #25: Please review Plan Sheet 362 of 1168 (DD-14). Details for RSP Lining and RSP Drop Structures are missing. Review and advise.
Inquiry submitted 06/13/2014

Response #1:Submitted for consideration.
Response posted 06/14/2014


Response #2:An addendum will be issued for clarification.

Response posted 06/16/2014




Inquiry #26: Reference plan sheet 492, Stage Construction Details. Typical Driveway Construction-Step 2 indicates a temporary crash cushion array. These crash cushions are not included with the Traffic Handling Quantities shown on sheet 646. Question, will the crash cushions for driveway construction be measured and paid for with Item 11-Temporary Crash Cushion Module? If yes, then the Engineer's Quantity of 420 each is severely understated. Please review.
Inquiry submitted 06/13/2014

Response #1:Submitted for consideration.
Response posted 06/14/2014


Response #2: An addendum will be issued to revise the quantity.

Response posted 06/16/2014




Inquiry #27: Reference plan sheet 492 displays a two (2) step process for installation of temporary K-rail when constructing the driveway entrances. The K-rail illustrated on these "typical" drawings appears to not be reflected in the total quantity for temporary K-rail nor depicted on the stage construction layout drawings. With 73 each driveways to be constructed, it would appear that the temporary K-rail quantity could increase significantly.

Would Caltrans please review and clarify the Temporary K-rail bid item?

Inquiry submitted 06/16/2014

Response #1:Submitted for consideration.

Response posted 06/16/2014


Response #2:An addendum will be issued to revise the quantity.

Response posted 06/16/2014




Inquiry #28: Reference Bid Item No. 172 – Pre/Post Construction Surveys – 7 each. In looking through the Special Provisions, we find references to Pre Construction Surveys in the following locations:
A. Page 39 – section 14-6.02C(5), item #13.
B. Page 43 – section 14-6.07A(3), item #15.
C. Page 78 – sections 73-3.01C and 73-3.01D.
Please provide a detailed description of what Bid Item No. 172 is intended to cover. Is it for “species protection” or is it for placement of minor concrete curb, sidewalk, and curb ramps? Also, please provide details of how the quantity of 7 each was determined.

Inquiry submitted 06/16/2014

Response #1:Submitted for consideration.

Response posted 06/16/2014


Response #2:Addendum will be issued for clarification.

Response posted 06/17/2014




Inquiry #29: Reference Bid Item No. 174 - Solar Community Light - 2 each. Plan sheet 183 shows two lights at Phelan Road and plan sheet 184 shows two lights at Hess Road. We assume that the bid quantity should be 4 each rather than 2 each. Please confirm that this is the case and that the intent was not that the quantity of 2 each is intended to cover any and all lights at the 2 each locations.
Inquiry submitted 06/16/2014

Response #1:Submitted for consideration.

Response posted 06/16/2014


Response #2:An addendum will be issued to revise quantity.

Response posted 06/17/2014




Inquiry #30: Reference Bid item #45 - Remove RCB (Cy)
#46 - Remove RCB (Ls)

Referring to drainage system 141-a, indicates remove RCB @ wildlife undercrossing (sht. 394 of 1168) Qtys = 115 cy. Referring to Wildlife Undercrossing Structural Plans (sht. 1123 of 1168) Qtys = 1 Ls.

Since both bid items seem to be referring to the same RCB to be removed, which one are we to use for bidding purposes. Please clarify.



Inquiry submitted 06/16/2014

Response #1:Submitted for consideration.
Response posted 06/16/2014


Response #2:An addendum will be issued for clarification.


Response posted 06/19/2014




Inquiry #31: Reference Plan Sheet 452 - Note #6. This note states to remove existing asphalt pavement on top of Pine Lodge East OH Bridge. Where is this work to be paid? The quantity for bid item #49 only covers the work for the Cajon Creek Bridge (widen). Is it the intent to also place polyester overlay on Pine Lodge Eash OH bridge? If so, the polyester quantities will need to be corrected.
Inquiry submitted 06/17/2014

Response #1:Submitted for consideration.
Response posted 06/17/2014


Response #2:Please see title sheet note, this bridge is not part of this project.

Response posted 06/19/2014




Inquiry #32: Section 19-3.01A(1) of the Specs states “Structure backfill includes constructing the geocomposite drain”. However, there is a bid item#155 for Geocompostie Drain, which according to the quantity summary in the Structure Plans seems to cover Soil Nail Wall #446 only. Please confirm which locations are paid under Item#155.
Inquiry submitted 06/17/2014

Response #1:Submitted for consideration.
Response posted 06/17/2014


Response #2:An Addenddum will be issued for clarification.
Response posted 06/24/2014


Response #3:Refer to Addenum No. 4 dated June 27, 2014. Bid item 155 has been deleted.
Response posted 07/10/2014




Inquiry #33: Reference response to Bid Inquiry No. 19. A few years ago a Caltrans project in District 11 bid where the bid date was changed from a Thursday to a Friday. One bidder faxed in the 24 hour sub listing form on the following Saturday. The remaining bidders faxed in the 24 hour sub listing form on the following Monday. A protest ensued, all bids were thrown out, and the job had to be re-bid. In order to avoid a potential protest, please confirm by addendum that the 24 hour sub lising form for this Contract must be faxed in by 2:00 pm on Monday, July 7th if the bid date is to remain as July 3rd.
Inquiry submitted 06/17/2014

Response #1:Submitted for consideration.
Response posted 06/17/2014


Response #2:Please refer to Addendum No. 4 issued on June 27, 2014.
Response posted 07/17/2014




Inquiry #34: On page 65 - DIVISION V SURFACINGS AND PAVEMENTS it stes "Add to section 39-1.02D3(a) of the RSS for section 39: Treat aggregate with lime slurry."
Section 39-1.02D(3)(a) is the General section for Aggregate Lime Treatments.
What is the intent of adding "Treat aggregate with Lime slurry".
Section 39-1.02 E Liquid Antistrip Treatment is STILL VALID.

Inquiry submitted 06/18/2014

Response #1:Submitted for consideration.
Response posted 06/18/2014


Response #2:The intent of adding "Treat aggregate with Lime slurry" is to require using lime slurry on the aggregate.


Response posted 06/19/2014




Inquiry #35: Section 5-1.20C states that "if the Contract includes an agreement with a railroad company, the Department makes the provisions of the agreement available in the Information Handout in the document titled Railroad Relations and Insurance Requirements. Please provide the necessary agreements.
Inquiry submitted 06/18/2014

Response #1:Submitted for consideration.
Response posted 06/18/2014


Response #2:There is no railroad involvement on this project.

Response posted 06/19/2014




Inquiry #36: Reference bid item No. 54 - Reconstruct Rock Slope Protection. Please provide details of what is required for this bid item. Is rock slope protection fabric required under the reconstructed RSP? If so, where is it paid? Also, during a site visit, it appears that the existing RSP on the "A" line from Sta 756+00 to 764+50 that is to be reconstructed has been concreted by others. Will the contractor be required to concrete the reconstructed RSP in this location?
Inquiry submitted 06/18/2014

Response #1:Submitted for consideration.
Response posted 06/18/2014


Response #2: Please see Standard Specifications 2010, section 15-2.04A General, page 220. Bid per current contract documents.


Response posted 06/19/2014




Inquiry #37: Reference plan sheet 399. The RSP Fabric (class 8) total quantity is shown as 3150 SY. The quantity for bid item No. 168 for RSP Fabric in only 1830 SY. Which is correct?
Inquiry submitted 06/18/2014

Response #1:Submitted for consideration.
Response posted 06/18/2014


Response #2:An addendum will be issued to revise the quantity.

Response posted 06/19/2014




Inquiry #38: Reference Plan Sheet 785 - Table of quantities for "Remove Asphalt Concrete Dike". The footnote states that this is for information only. Standard Specifications section 15-2.02F - "Remove Asphalt Concrete Dikes" is "reserved", with no clarification provided in the Special Provisions for that section. Where is the cost of removing the 27,205 LF of AC Dike to be paid?
Inquiry submitted 06/19/2014

Response #1:Submitted for consideration.
Response posted 06/19/2014


Response #2:Please refer to Standard Specifications 2010, section 9-1.03 PAYMENT SCOPE.
Response posted 06/24/2014




Inquiry #39: Re: Addenda #3

What changes have occurred on plan sheets 362,369, & 452?

in the future it would be helpful if you would bubble the changes made, so that they are easier to spot.

Inquiry submitted 06/23/2014

Response #1:Submitted for consideration.
Response posted 06/23/2014


Response #2:Changes to the plan sheets for Addendum N0.3 are as follows:

Sheet No. 362 Detail was added.
Sheet No. 369 No change
Sheet No. 452 Note No. 1 has been modified.

Response posted 06/25/2014




Inquiry #40: Re: Addenda #3

What changes have occurred on plan sheets 362,369, & 452?

in the future it would be helpful if you would bubble the changes made, so that they are easier to spot.

Inquiry submitted 06/23/2014

Response #1:Submitted for consideration.
Response posted 06/23/2014


Response #2:Changes to the plan sheets for Addendum N0.3 are as follows:

Sheet No. 362 Detail was added.
Sheet No. 369 No change
Sheet No. 452 Note No. 1 has been modified.

Response posted 06/25/2014




Inquiry #41: We respectfully request the bid date be extended for the project. The project is currently bidding the day before July 4th, a major holiday. Due to the holiday, prime contractors may receive a reduced number of quotes from subcontractors and suppliers that are taking time off. We request that the bid date be extended so that we can provide a complete and competitive bid.
Inquiry submitted 06/23/2014

Response #1:Submitted for consideration.
Response posted 06/23/2014


Response #2:Please see Addendum NO. 4 issued on June 27, 2014.
The Bid Opening has been postponed to July 24, 2014.
Response posted 06/27/2014




Inquiry #42: We respectfully request the bid date be extended for the project. The project is currently bidding the day before July 4th, a major holiday. Due to the holiday, prime contractors may receive a reduced number of quotes from subcontractors and suppliers that are taking time off. We request that the bid date be extended so that we can provide a complete and competitive bid.
Inquiry submitted 06/23/2014

Response #1:Submitted for consideration.
Response posted 06/23/2014


Response #2:Please see Addendum NO. 4 issued on June 27, 2014.
The Bid Opening has been postponed to July 24, 2014.
Response posted 06/27/2014




Inquiry #43: We respectfully request the bid date be extended for the project. The project is currently bidding the day before July 4th, a major holiday. Due to the holiday, prime contractors may receive a reduced number of quotes from subcontractors and suppliers that are taking time off for the holiday. We request that the bid date be extended so that we can provide a complete and competitive bid.
Inquiry submitted 06/23/2014

Response #1:Submitted for consideration.
Response posted 06/23/2014


Response #2:Please see Addendum NO. 4 issued on June 27, 2014.
The Bid Opening has been postponed to July 24, 2014.
Response posted 06/27/2014




Inquiry #44: We respectfully request the bid date be extended for the project. The project is currently bidding the day before July 4th, a major holiday. Due to the holiday, prime contractors may receive a reduced number of quotes from subcontractors and suppliers that are taking time off. We request that the bid date be extended so that we can provide a complete and competitive bid.
Inquiry submitted 06/23/2014

Response #1:Submitted for consideration.
Response posted 06/23/2014


Response #2:Please see Addendum NO. 4 issued on June 27, 2014.
The Bid Opening has been postponed to July 24, 2014.
Response posted 06/27/2014




Inquiry #45: In reference to question #39 & #40.

Caltrans response was that there was a detail added to sheet 362 for addenda #3.

Question - What detail? please check the addenda #3 that was sent out, since no detail was included.+

Inquiry submitted 06/25/2014

Response #1:Submitted for consideration.
Response posted 06/25/2014


Response #2:An addendum will be issued to show the detail.
Response posted 06/26/2014




Inquiry #46: The AC Spec on sheet 170 of 324 states "For HMA mixtures using RAP, the max binder replacement is 25% for surface course and 40% for lower courses". On sheet 173 of 324 it states "You may substitute RAP for part of the virgin aggregate in a quantity up to a max of 25% of the aggregate blend". What is the max RAP use for this project?
Inquiry submitted 06/25/2014

Response #1:Submitted for consideration.
Response posted 06/25/2014


Response #2:25% is the maximum RAP allowed as long as the binder replacement requirements of 25% surface course, and 40% lower courses are not exceeded. Bid per current contract documents.
Response posted 06/30/2014




Inquiry #47: We also respectfully request that 08-3401U4 be postponed several weeks to allow thorough coverage from our subcontractors, vendors, and our own support staff. The week before the 4th of July and the week after the 4th of July are typically weeks that many employees schedule and take their summer vacations. Our company is no exception, with many employees already having scheduled out of town events during this period.
Inquiry submitted 06/25/2014

Response #1:Submitted for consideration.
Response posted 06/25/2014


Response #2:Please see Addendum NO. 4 issued on June 27, 2014.
The Bid Opening has been postponed to July 24, 2014.
Response posted 06/27/2014




Inquiry #48: Bid Item 155 Geocomposite Drain. Bid quantity reflects quantity for Wall 446 (4644 sf). Geocomposite drain is also shown on Wall 372, plus 3 of the bridges. Will the bid quantity be revised to reflect the other geocomposite drain or will this additional drain be paid for under different items? Please clarify.
Inquiry submitted 06/26/2014

Response #1:Submitted for consideration.
Response posted 06/26/2014


Response #2:An Addendum will be issued to address this inquiry.
Response posted 06/27/2014


Response #3:Refer to Addendum No. 4 dated June 27, 2014. Bid item 155 has been deleted. And also, please refer to Section 19-3.01A of the special provisions.
Response posted 07/10/2014




Inquiry #49: We would like to request that the bid date NOTE be postponed. This project has been out for bid nearly two months, which is more than adequate time for subcontractors and prime contractors to analyze the project and provide competitive pricing.
Inquiry submitted 06/26/2014

Response #1:Submitted for consideration.
Response posted 06/26/2014


Response #2:Please see Addendum NO. 4 issued on June 27, 2014.
The Bid Opening has been postponed to July 24, 2014.
Response posted 06/27/2014




Inquiry #50: Wondering when we can expect answers to inquiry Nos. 15, 30, 33, and 45?
Inquiry submitted 06/26/2014

Response #1:Submitted for consideration.
Response posted 06/26/2014


Response #2:Response to inquiries are posted as information is available. Please see specific inquiry for response.
Response posted 07/17/2014




Inquiry #51: The Wildlife Undercrossing sheet 1127 section C-C, sheet 1128 section F-F indicate slotted drain pipe with filter fabric and TPB. The drawing do not indicate where this drainage is discharging as these areas are approximately six (6’) feet below finish grade. The wall drawing elevations and drawing plans do not show the weep hole locations. Please clarify the locations of weep holes and is the lower drainage on top of the footing required.
Inquiry submitted 06/26/2014

Response #1:Submitted for consideration.

Response posted 06/26/2014


Response #2:An addendum will be issued for clarification.

Response posted 07/16/2014




Inquiry #52: We respectfully request bid date be delayed for a least a week, due the July 4th holiday.
Inquiry submitted 06/26/2014

Response #1:Submitted for consideration.
Response posted 06/26/2014


Response #2:Please see Addendum NO. 4 issued on June 27, 2014.
The Bid Opening has been postponed to July 24, 2014.
Response posted 06/27/2014




Inquiry #53: Didn't find any details for Item #191 - Cable Railing (Modified), want to check what was modified from Caltrans Std. Plan B11-47 (Item #190 - Cable Railing). Please verify. Thanks
Inquiry submitted 06/26/2014

Response #1:Submitted for consideration.
Response posted 06/26/2014


Response #2:An addendum will be issue for clarification.

Response posted 07/16/2014




Inquiry #54: Can't find the locations and lay-out for Item #197 - Crash Cushion Module, Sand Filled - 28 EA. Please check. Thank you.
Inquiry submitted 06/26/2014

Response #1:Submitted for consideration.

Response posted 06/26/2014


Response #2:An addendum will be issued for clarification.
Response posted 07/17/2014




Inquiry #55: Reference Special Provisions page 37 - Section 14 - Environmental Stewardship. The second sentence of the second paragraph under this section states "Install temporary SILT fence with Type ESA Temporary Fence as shown on the plans. We assume, unless otherwise clarified by addendum that all silt fence installed on the project will be paid under bid item no. 23, and will not be incidental to bid item no. 28. Please confirm.
Inquiry submitted 06/27/2014

Response #1:Submitted for consideration.
Response posted 06/27/2014


Response #2:Bid per current contract documents.

Response posted 07/16/2014




Inquiry #56: Is the HMA to be used on this project required to use lime treated aggs or will liquid anti-strip be allowed?
Inquiry submitted 06/27/2014

Response #1:Submitted for consideration.
Response posted 06/27/2014


Response #2:Lime slurry is required and liquid anti-strip will not be allowed.

Response posted 07/16/2014




Inquiry #57: Reference Plan Sheet 1078, drawing Section A-A. There is a note that states "Paving Notch Extension, if required". Is a Paving Notch Extension required? If so, where is it paid? There is typically a bid item for Paving Notch Extensions (item code 510800).
Inquiry submitted 07/01/2014

Response #1:Submitted for consideration.
Response posted 07/01/2014


Response #2:An addendum will be issued to revise the quantity.
Response posted 07/10/2014




Inquiry #58: Reference Bid Item No. 117. Please provide a detail for and location of the Aggregate Base (Approach Slab).
Inquiry submitted 07/01/2014

Response #1:Submitted for consideration.
Response posted 07/01/2014


Response #2: A detail is not included on the plans for Item No. 117 Aggregate Base(Approach Slab) . Aggregate Base (Approach Slab) is placed as required per field conditions. Bid per current contract documents.

Response posted 07/07/2014




Inquiry #59: On the Front Page of the specs under "SPECIAL NOTICES" It states that the department has revised its HMA specs to the Superpave design method and that we are to see the RSS section 39.

Q - Referring to RSS section 39, this is not the Superpave spec. Please clarify

Inquiry submitted 07/02/2014

Response #1:Submitted for consideration.
Response posted 07/02/2014


Response #2:For Hot Mix Asphalt, bid per current contract documents.

Response posted 07/16/2014




Inquiry #60: Item 32, Contract Biologist, is a lump sum. What is the expected amount of biological monitoring time on the project?
Inquiry submitted 07/07/2014

Response #1:Submitted for consideration.
Response posted 07/07/2014


Response #2:Expected amount of biological monitoring is for duration of the project.
Response posted 07/17/2014




Inquiry #61: It appears from the Drainage Quantities Summary on plan sheet 399 that the 170 LF of Jacked 36" RCP (Bid Item #177) is included in the 260 LF of 36" RCP (Bid Item #143). Per special provisions page 79, section 78-2.02A(1), the jacked pipe item includes FURNISHING and installing the RCP. Please revise the quantity for bid item #143 to reflect only the 36" RCP that is not jacked.
Inquiry submitted 07/08/2014

Response #1:An addendum will be issued to revise the quantity.
Response posted 07/10/2014




Inquiry #62: Reference Plan Sheet 395 - column for 24" RCP. It appears that the quantities for Drainage System Nos. 149b, 149d, 149h, 149j, 149l, and 149n (173 LF) were not included in the quantity for bid item #142 - 24" RCP. The 190 LF in bid item #142 covers the 24" RCP quantities shown on Plan Sheets 388 and 389. Please correct the quantity for bid item #142.
Inquiry submitted 07/08/2014

Response #1:An addendum will be issued to revise the quantity.
Response posted 07/10/2014




Inquiry #63: Will you please publish the Mandatory Pre-Bid Attendee list from the June 5th pre-bid meeting? Thank you.
Inquiry submitted 07/16/2014

Response #1:Copies of the sign-in sheets for Primes and Subs who attended the mandatory meeting for project # 08-3401U4 on June 5, 2014 are available.
To obtain a copy by email, Please send a request email to:
d8.pbi@dot.ca.gov and the sign-in sheets will be sent back to you.
Response posted 07/16/2014




Inquiry #64: Reference Bid Item No. 204 - Concrete Barrier (Type 60D Modified) - bid quantity shown as 1260 LF. We only find 220 LF as shown on plan sheet 781 in the Retaining Wall Quantities for RW 743. Please provide the location of the remaining 1040 LF of Type 60D Modified barrier.
Inquiry submitted 07/17/2014

Response #1:Submitted for consideration.

Response posted 07/17/2014


Response #2:Response: For additional quantity see structure plans.

Response posted 07/19/2014




Inquiry #65: Does this project require inertial profiler testing?
Inquiry submitted 07/18/2014

Response #1:Submitted for consideration.
Response posted 07/19/2014


Response #2:Yes, project requires inertial profiler testing.

Response posted 07/22/2014




Inquiry #66: PLAN SHEET 919 NOTE 3 REFER TO STRUCTURE DETAILS. WHICH PLAN SHEETS IS THE NOTE REFERRING TO AS WE COULD NOT FIND THEM.
Inquiry submitted 07/21/2014

Response #1:Submitted for consideration.

Response posted 07/21/2014


Response #2:Please refer to title sheet, structure is not part of the project.

Response posted 07/22/2014




Inquiry #67: WHAT TYPES OF POLE ASSEMBLIES ARE USED IN BID ITEM 215. THE PLANS DOE NOT DESCRIBE THEM.
Inquiry submitted 07/21/2014

Response #1:Submitted for consideration.

Response posted 07/21/2014


Response #2:Refer to RSP ES-1B and RSP-7J for Flashing Beacon.

Response posted 07/22/2014




Inquiry #68: REFER TO PLAN SHEET 845 NOTE 1 FOR SHEETS E-1 TO E-10. PLEASE CONFIRM THAT PB DETAIL REFERENCED SHALL ONLY BE USED WHEN NOTES AS DID ON SHEET 845.
Inquiry submitted 07/21/2014

Response #1:Submitted for consideration.
Response posted 07/21/2014


Response #2:Please follow plan note 1 as indicated.

Response posted 07/22/2014






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.