Inquiry #1: On sheet tE-3, a 3" conduit has 4 DLC and 2 STC crossing SR 190. Only two loops, and one piezo detector are shown on the plans. Are the extra DLC and STC cables for future use, or should there be additional loops and piezos, or should the extra cable be eliminated?
Inquiry submitted 08/01/2017

Response #1:Submitted for consideration.
Response posted 08/01/2017


Response #2:Conductors shown on the plan are required for the system; no additional loops or piezo sensors are required. Bid per current contract documents.
Response posted 08/02/2017




Inquiry #2: Section 30-5.03C(2) Cold-Planing Equipment requires a 12 foot wide cutter. Plan Sheet X-2 cross section calls for a 8' to 10' wide section. The CIPR mill is 12 foot wide. Please advise.
Inquiry submitted 08/11/2017

Response #1:Submitted for consideration.
Response posted 08/14/2017


Response #2:"A cold-planing machine with a cutter narrower than 12 feet wide may be used for shoulders and miscellaneous areas" per the last paragraph of the referenced section.
Response posted 08/22/2017




Inquiry #3: Section 30-5.01D(4)(d) Smoothness states "Correct MRI greater than 75 in/mi for a 0.1-mile section and areas of localized roughness greater than 180 in/mi". Will an Addendum be issued to reflect the latest Standard of "Correct MRI greater than 90 in/mi for a 0.1-mile section and areas of localized roughness greater than 240 in/mi".
Inquiry submitted 08/11/2017

Response #1:Submitted for consideration.
Response posted 08/14/2017


Response #2:Refer to Addendum No. 1, dated August 18, 2017.
Response posted 08/22/2017




Inquiry #4: Will CalTrans supply a drill log for the CMS sign structure foundation? There appears to be flood irrigation in this area and might affect the installation of the sign structure foundation.
Inquiry submitted 08/14/2017

Response #1:Submitted for consideration.
Response posted 08/14/2017


Response #2:No drill log is available. Bid per current contract documents.
Response posted 08/22/2017




Inquiry #5: On sheet 3 and 4 of the plan sheets the typical cross sections call out for the contractor to remove AC pavement from the existing Eastbound lanes. This is a substantial quantity, and it does not appear to be included in the roadway Ex quantity. Will the state please add a bid item for Remove AC pavement per CY, which is Caltrans Item code 398000?
Inquiry submitted 08/17/2017

Response #1:Submitted for consideration.
Response posted 08/18/2017


Response #2:Refer to Addendum No. 3, dated September 1, 2017.
Response posted 09/06/2017




Inquiry #6: On sheet 117 of the plans there is an HMA quantity for detours. Where, how many locations, and how deep is the HMA for the detours??
Inquiry submitted 08/24/2017

Response #1:Submitted for consideration.
Response posted 08/25/2017


Response #2:Refer to Addendum No. 3, dated September 1, 2017.
Response posted 09/06/2017




Inquiry #7: Item 30 "Emulsified Recycling Agent" Bid Quantity of 30 tons is very low. Please confirm quantity should be closer to around 190 tons?
Inquiry submitted 08/25/2017

Response #1:Submitted for consideration.
Response posted 08/28/2017


Response #2:Refer to Addendum No. 3, dated September 1, 2017.
Response posted 09/06/2017




Inquiry #8: Does the SAMI-R have to be paved over every shift prior to opening to traffic per Section 37-2.05 of the RSS?
Inquiry submitted 08/29/2017

Response #1:Submitted for consideration.
Response posted 08/30/2017


Response #2:
Bid per current contract documents.
Response posted 09/13/2017




Inquiry #9: The SAMI-R Quantities seem to be off.

AR Binder should be .55-.65 Gallons per SY and Precoated Screenings should be 28-40 lbs per SY.

Please verify.

Inquiry submitted 08/30/2017

Response #1:Submitted for consideration.
Response posted 08/30/2017


Response #2:
Bid per current contract documents.
Response posted 09/13/2017




Inquiry #10: What is the required gradation for the Precoated Screenings?
Inquiry submitted 08/31/2017

Response #1:Submitted for consideration.
Response posted 09/05/2017


Response #2:Refer to Standard Specification
37-2.06 STRESS ABSORBING MEMBRANE INTERLAYER
37-2.06A General
Section 37-2.06 includes specifications for placing stress absorbing membrane interlayer(SAMI).
37-2.06B Materials
Screenings must comply with the 3/8-inch maximum gradation.
Response posted 09/06/2017




Inquiry #11: Please add a specification for the gradation of bid item 35, precoated screenings.
Inquiry submitted 09/05/2017

Response #1:Submitted for consideration.
Response posted 09/05/2017


Response #2:Refer to Standard Specification
37-2.06 STRESS ABSORBING MEMBRANE INTERLAYER
37-2.06A General
Section 37-2.06 includes specifications for placing stress absorbing membrane interlayer(SAMI).
37-2.06B Materials
Screenings must comply with the 3/8-inch maximum gradation.
Response posted 09/06/2017




Inquiry #12: In Addendum #3 the AC number was revised up by 4,200 tns. The detour appears to have been deleted in the Detour Quantities grid but not the HMA quantities. Instead of removing the detour line on the quantity sheet it was not only left in but added in again. Now the item is overstated by 8,400 tons. Please remove the 8,400 tons OR clarify where the detour is and and where the additional AC came from in the HMA (Type A) Roadway Quantities Grid.
Inquiry submitted 09/12/2017

Response #1:
Submitted for consideration.
Response posted 09/12/2017


Response #2:
Bid per current contract documents.
Response posted 09/13/2017




Inquiry #13: Addendum #3 is showing a new revised Road Ex and Embankment quantity. Please clarify with revised plan sheets and cross sections the additional cuts and fills required by this change so we can perform takeoffs and price accordingly.
Inquiry submitted 09/12/2017

Response #1:
Submitted for consideration.
Response posted 09/12/2017


Response #2:
Bid per current contract documents.
Response posted 09/13/2017




Inquiry #14: On Plan Sheet #117 of Addendum #3 there is a line item for detours of 4,200 tons in the Roadway Quantities which makes is part of the total tons of AC to be placed. Please provide details and locations of these detours since they are still included in AC quantity.
Inquiry submitted 09/13/2017

Response #1:
Submitted for consideration.
Response posted 09/13/2017


Response #2:
Bid per current contract documents.
Response posted 09/15/2017




Inquiry #15: On sheet 3 and 4 of the plan sheets the typical cross sections call out for the contractor to remove AC pavement from the existing Eastbound lanes. Much of this area is outside the Road Ex grading prism. Please clarify how this to be paid and graded, if grading is required after removal.
Inquiry submitted 09/13/2017

Response #1:
Submitted for consideration.
Response posted 09/13/2017


Response #2:
Bid per current contract documents.
Response posted 09/15/2017




Inquiry #16: When trying to download the E-Bid file for addendum #6; instead of receiving an addenda file when the download button is pushed, the contractor is re-directed to the Bid express website. Please advise and update the E-Bid addenda file for addendum #6.
Inquiry submitted 10/16/2017

Response #1:
As it is marked on Caltrans website, under All Projects Currently Advertised:

"Beginning with projects advertised, or addenda issued on or after October 16, 2017, electronic bid files i.e. bid books and addenda, will be distributed through the Bidx.com website. These electronic bid files will no longer be available on the Caltrans website."

Response posted 10/16/2017






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, “JOB SITE AND DOCUMENT EXAMINATION” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.