Viewing inquiries for 05-1H4004

Submit new inquiry for this project


Inquiry #1: Special provision section 12-9.01A (COZEEP) requires contractors to share in the cost 50/50 for up to 900 hours, then 100% contractors responsibility beyond the allocated hours. Will COZEEP be ordered during ramp closures when mainline will remain open?

Section 12-9.04 (Payment) states the rate per hour for each officer is $115.00 per hour. Does this rate include unlimited shift hours, or does overtime apply after a certain amount of hours?

Inquiry submitted 04/09/2017

Response #1:
Submitted for consideration.
Response posted 04/10/2017


Response #2:
The COZEEP rate per hour listed in SSP 12-9 applies for the entire shift allowed per the contract lane and ramp closure charts.

For purposes of this project bid that COZEEP will not be required for a ramp closure with no associated mainline lane closure. Per SSP 12-9 the Engineer will make the ultimate decision if COZEEP is required based on work activities and duration.

Response posted 04/11/2017






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, “JOB SITE AND DOCUMENT EXAMINATION” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.