Viewing inquiries for 05-1A3404

Submit new inquiry for this project


Inquiry #1: Per the specifications the utility owner will adjust frames and covers for this project. Who will be responsible for costs to lower the utilities prior to cold planing, the utility owner or the contractor?
Inquiry submitted 12/16/2013

Response #1:Submitted for consideration.
Response posted 12/16/2013


Response #2:Reference Special Provision, section 5-1.36D Control of Work, and Standard Specifications; section 51-1.03E (9) Utility Facilities. The utility owner will be responsible for cost of lowering the utilities prior to cold planning.
Response posted 12/17/2013




Inquiry #2: Is the contractor responsible for providing traffic control for the utility company's adjustment work?
Inquiry submitted 12/16/2013

Response #1:Submitted for consideration.
Response posted 12/16/2013


Response #2:No. Reference Standard Specifications; section 5-1.20 Coordination With Other Entities and section 5-1.36D Non highway Facilities.
Response posted 12/17/2013




Inquiry #3: Per the specifications the maximum length of a single stationary one-way reversing traffic control lane closure is 1/4 miles? Is the 1/4 mile length correct, this seems cost prohibitive?
Inquiry submitted 12/16/2013

Response #1:Submitted for consideration.
Response posted 12/16/2013


Response #2: Refer to Addendum No. 1 dated December 18, 2013: "The maximum length of a single stationary one-way reversing traffic-control lane closure is 1/2 mile between the flaggers."
Response posted 12/23/2013




Inquiry #4: Is the contractor responsible for adjusting the existing survey monuments in the roadway? If yes, how many survey monuments are in the paving area and in what bid item should this work be included?
Inquiry submitted 12/16/2013

Response #1:Submitted for consideration.
Response posted 12/16/2013


Response #2:No. Contractor must protect existing highway facilities.
Response posted 12/18/2013




Inquiry #5: What is the cold plane & HMA conform detail for the typical residential (private) driveway on this project?
Inquiry submitted 12/19/2013

Response #1: Submitted for consideration.
Response posted 12/23/2013


Response #2:No detail is needed. Bid per current contract documents.
Response posted 01/02/2014






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.