Inquiry #1: In reference to a sentence on page 13 of the specifications, "Except for one way reversing traffic control lane closures, the maximum length of the work area inside a closure is 1000ft"

Will this apply to stationary lane closures at location No. 4? That would be approximately 240 lane closures?

Inquiry submitted 07/19/2017

Response #1:Submitted for consideration.
Response posted 07/19/2017


Response #2:Yes, the sentence "Except for one way reversing traffic control lane closures, the maximum length of the work area inside a closure is 1000ft" applies to location No. 4.
Response posted 07/21/2017




Inquiry #2: In reference to the lengths of the traffic control closure restrictions (500 feet for the flagging and 1000 feet for the lane closures) this is going to increase the number of traffic control shifts and elevate the costs for the bid item for Traffic Control. By allowing for longer closures it will mean that the traffic control crews will be less exposed to potential danger. It will also speed the progress of the project allowing for faster completion and this will directly impact both the safety and convenience of the traveling public.
Inquiry submitted 07/21/2017

Response #1:Submitted for consideration.
Response posted 07/24/2017


Response #2:This project bid opens on Wednesday, July 26. Please bid per plans and specs.
Response posted 07/25/2017




Inquiry #3: For Item 10-Temporary Construction Entrance neither the project plans nor the project special provisions identify which of the 2 different versions (Type 1 and Type 2) is specified for this project. Please Clarify
Inquiry submitted 07/24/2017

Response #1:Submitted for consideration.
Response posted 07/24/2017


Response #2:For Item 10-Temporary Construction Entrance, please use Type 1.
Response posted 07/25/2017






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, “JOB SITE AND DOCUMENT EXAMINATION” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.