Inquiry #1: ITEM #30, CONCRETE BARRIER, TYPE 60:
Project Plans refer to the Barrier as Type 60C. Will Bid Item #30 be corrected?

Inquiry submitted 08/14/2017

Response #1:Submitted for consideration.
Response posted 08/14/2017


Response #2:See Addendum 1.
Response posted 08/21/2017




Inquiry #2: item 4 - Temporary K-rail shows 20 LF. Plan sheet Q-1 shows 1000LF. Will the quantities be updated?
Inquiry submitted 08/15/2017

Response #1:Submitted for consideration.
Response posted 08/21/2017


Response #2:Q sheet quantity is correct (1,000 LF of Temporary K-Rail).
Response posted 08/21/2017




Inquiry #3: I didn't see an ADL report. We need an ADL report to determine if additional sampling is required for disposal at a California Class I landfill.
Inquiry submitted 08/16/2017

Response #1:Submitted for consideration.
Response posted 08/21/2017


Response #2:You can download the Preliminary Site Investigation Report below:

www.dot.ca.gov/dist4/construction/contracts/04-4G4904/4G4904_SIReport.pdf


Response posted 08/21/2017




Inquiry #4: Are cross sections available for this project?
Inquiry submitted 08/21/2017

Response #1:Submitted for consideration.
Response posted 08/22/2017


Response #2:See Cross Sections below:

://www.dot.ca.gov/dist4/construction/contracts/04-4G4904/XSections.pdf
Response posted 08/29/2017




Inquiry #5: You have answered the question regarding the disparity of footage for K-Rail. Are you going to issue an addendum to correct the quantity from 20 ft to 1,000 ft?

There is no pay item for traffic control - how is the traffic control to be paid?

Is there any supplemental geotech report for this project? There is an 8 ft deep junction structure on the project. We would like to know if there is a potential for ground water intrusion.

Inquiry submitted 08/25/2017

Response #1:Submitted for consideration.
Response posted 08/25/2017


Response #2:a) See Addendum 2.

b) Traffic Control is paid under Maintain Traffic ( item no. 066070) with Lump Sum of $ 132,000. See Addendum 4.

c) The project does not qualify for full geotechnical report . There are no retaining walls or bridges or deep cuts or fills. The Drainage is a spot location and any water encountered will be handled per Standard specs for dewatering.
Response posted 08/28/2017




Inquiry #6: Can the state please provide cross sections that are required to determine the offset of the Type 60C Barrier.
Inquiry submitted 08/25/2017

Response #1:Submitted for consideration.
Response posted 08/28/2017


Response #2:The State can provide the winning bidder a survey to layout the centerline of the barrier or layout line of the barrier(it may not be centerline of barrier) along with survey slope stakes.
Response posted 08/30/2017




Inquiry #7: The special provisions provide for a shoulder closure only under the traffic control section. However, in order to set & remove K-rail and to cut in the drainage pipe at DU No. 2f which crosses the ramp, a ramp closure will be necessary. What times will be allowed for a ramp closure?
Inquiry submitted 08/25/2017

Response #1:Submitted for consideration.
Response posted 08/28/2017


Response #2:No Ramp closure. The work can be done in two stages as is typically done.
Response posted 08/29/2017




Inquiry #8: Can the state please add a pay item to the bid documents for traffic control. Per inquiry #5 it has been said that it's paid under maintain traffic control system but that item does not exist on bid documents. Also where is the $132,000 lump sum coming from and can that be shown on bid documents?
Inquiry submitted 08/28/2017

Response #1:Submitted for consideration.
Response posted 08/28/2017


Response #2:See Addendum 4.
Response posted 09/06/2017




Inquiry #9: A ramp closure will be required to set Temp K-Rail and to pickup. There is not enough room to have a through lane and equipment under a shoulder closure.
Inquiry submitted 08/29/2017

Response #1:Bid per plans and specs. Winning bidder can present the need of a full ramp closure with the RE.
Response posted 08/30/2017






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, “JOB SITE AND DOCUMENT EXAMINATION” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.