Viewing inquiries for 04-235624

Submit new inquiry for this project


Inquiry #1: The variable asphalt on the project varies between 0.10'-1.9'. Can we get cross sections for the RD Line 316+69-322+22.16 and the RC Line 10+98.28-15+55? Thanks
Inquiry submitted 02/02/2015

Response #1:Submitted for consideration.
Response posted 02/03/2015


Response #2:You can download the cross sections below:

www.dot.ca.gov/dist4/construction/contracts/04-235624/XSections_BI1.zip (zipped pdf, 3MB, updated 2/11/15)
Response posted 02/04/2015




Inquiry #2: “On page 53 of the specifications there is a requirement for a maximum Los Angeles Rattler of 25 at 500 Revolutions. It is industry’s understanding that this provision is a Non Standard Special Provision (NSSP) reserved for use in District 2 only. It is also industry’s understanding that when NSSP are used outside of their designated area (District or County) they will be removed via the Bidders Inquiry process. Will this provisions be removed.“
Inquiry submitted 02/06/2015

Response #1:Submitted for consideration.
Response posted 02/09/2015


Response #2:See Addendum 3.
Response posted 03/04/2015




Inquiry #3: Bid item 25 Temporary Construction Roadway - Please indicate where the location and details for this bid item are located and the specification sections which apply.
Inquiry submitted 02/11/2015

Response #1:Submitted for consideration.
Response posted 02/12/2015


Response #2:See Addendum 3.
Response posted 03/04/2015




Inquiry #4: The drill and bond dowel details for the abutment and pier walls seem to lack clarity. Is it the intent that the dowels follow the horizontal #5 bars in the pier and abutment walls? That is, 2 dowels per row @ 1' or 1/2' centers for the full height of the wall at each construction joint?
Inquiry submitted 02/19/2015

Response #1:Submitted for consideration.
Response posted 02/20/2015


Response #2:Yes, please bid per the current contract documents.
Response posted 02/23/2015




Inquiry #5: The Temporary K-Rail table on Sheet SCQ-4 does not include all of the k-rail locations shown on the Stage Construction Plans. Can Caltrans either update the table or revise the Stage Construction Plans to reflect the locations listed in the table?
Inquiry submitted 02/23/2015

Response #1:Submitted for consideration.
Response posted 03/04/2015




Inquiry #6: The front of the abutments and the piers are backfilled with structure backfill. Shouldn't there be a bid item for this work or can you tell us where this will be paid for if no bid item is provided?
Inquiry submitted 02/25/2015

Response #1:Submitted for consideration.
Response posted 02/25/2015


Response #2:The structure backfill at the front of the abutments and the piers is included in the payment for the type of structure excavation involved. Please refer to paragraph 10 in section 19-3.03E(1) and paragraph 8 in section 19-3.04 of the standard specifications.
Response posted 03/04/2015




Inquiry #7: The Minor Concrete (Curb, Sidewalk, Curb Ramp) table on Sheet Q-1, shows 20.7 CY of concrete for Sta. RFR 323+90 to 325+00. The plans do not show any curb and gutter or sidewalk in this area. They do show an A1-6 curb, but the quantity is not 20.7 CY. Also, the table shows 3.0 CY of concrete for Sta. RFL 323+50 to 324+40. The plans show 6" sidewalk and curb and gutter and also A1-6 curb. This quantity is not 3.0 CY. Can Caltrans look at this table and revise the quantities if necessary?
Inquiry submitted 02/26/2015

Response #1:Submitted for consideration.
Response posted 03/04/2015




Inquiry #8: Please confirm if attendance at the prebid meeting held on Feb 24th was required or mandatory? How can we get a copy of the attendees at this meeting?
Inquiry submitted 02/26/2015

Response #1:Submitted for consideration.
Response posted 02/27/2015


Response #2:The prebid meeting on Feb 24 was not mandatory. You can see the list of attendees from the pdf file below:


List of Attendees
Response posted 03/02/2015




Inquiry #9: Is the slide presentation from the prebid meeting available for viewing?
Inquiry submitted 03/02/2015

Response #1:You can download a pdf file of the slide show below:

Slides
Response posted 03/02/2015






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.