Viewing inquiries for 03-1H2604

Submit new inquiry for this project


Inquiry #1: Sheet W-8 has a note to "install near altitude valve to prevent overflow." Is the contractor responsible to supply and install an altitude valve for the water tank?
Inquiry submitted 09/11/2017

Response #1:Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 09/11/2017


Response #2:
Your attention is directed to the NOTE on project plan sheet 21 of 21, W-8, which states:

All items are existing except new items are called out by letter (N).

The water tank and altitude valve are existing.
Please bid per the current contract documents.
Response posted 09/11/2017






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, “JOB SITE AND DOCUMENT EXAMINATION” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.