Viewing inquiries for 02-4E6104

Submit new inquiry for this project


Inquiry #1: Item number 9 calls out for Treated wood waste which is reflected in the bid quantities towards the MBGR. We only have an item to Reset Guardrail (Item 13). Which calls out to reuse the existing material located on the job. Does Caltran want us to remove the existing post and blocks then dispose of them and then replace with new post and blocks?
Inquiry submitted 01/16/2014

Response #1:1/16/14: Your inquiry has been received and is being reviewed. Thank you for your patience.
Response posted 01/16/2014


Response #2:1/23/14: Please refer to the second paragraph of Section 15-2.08D(2) of the Special Provisions. Please bid per the current contract documents.
Response posted 01/23/2014




Inquiry #2: Sorry about posting a question this late. Page 247, 59-7 Staining Concrete & Shotcrete is asking to prepare and stain concrete and shotcrete surfaces using an acid stain. There is very little concrete exposed, is there any concrete that needs to be stained on this project? Do we have use the stain material in 59-7.01B(2) on the rock surface since 59-12.02B is reserved or can we use Permeon on the Rocks? Thanks,
Inquiry submitted 01/28/2014

Response #1:01/28/14: Your inquiry is under review. Please note that due to the current time frame between the inquiry submittal and the bid opening date, a response may not be provided before the bid opening. If a response is not provided before the bid opening addressing your concern, please bid per the current contract documents. Thank you for your patience.
Response posted 01/28/2014


Response #2:01/29/14: Please bid per current contract documents.
Response posted 01/29/2014






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.