Dept. of Trans. PROGRESS Serial No. Contract No. 09-058-11-08 12-0H9404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 77% 12-ORA-57-21.2/ .0 Federal Project: NONE Progress payment No. 06 Payment period ending: 02-20-09 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 926145706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 294,466.50 25,565.00 2.a. Extra Work 34,708.84 7,776.93 b. Adjustment Comp. 3. Materials on Hand 26,000.00 -25,648.01 4. Earned Subject to Retention 355,175.34 7,693.92 5. Mobilization 25,000.00 0.00 6. Total Work Completed 354,175.34 7. Deductions -1,000.00 -1,000.00 8. a.Contract Retentions -17,758.77 -384.70 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 361,416.57 6,309.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,309.22