Dept. of Trans. PROGRESS Serial No. Contract No. 10-327-07-11 12-0E0704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 12-ORA-5-15.1/16.4 Federal Project: NONE Progress payment No. 28 Payment period ending: 11-20-10 ORTIZ ENTERPRISES INCORPORATED 6 CUSHING SUITE 200 IRVINE CA 92618 Escrow No. 02398 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,420,227.66 21,605.00 2.a. Extra Work 467,529.32 9,913.17 b. Adjustment Comp. -172,898.51 0.00 3. Materials on Hand 198,283.92 0.00 4. Earned Subject to Retention 10,913,142.39 31,518.17 5. Mobilization 1,260,000.00 0.00 6. Total Work Completed 11,974,858.47 7. Deductions -1,102.50 0.00 8. a.Contract Retentions -545,657.12 -1,575.91 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,626,382.77 29,942.26 10. Reduction Amt to Escrow 11. Payment to Escrow 545,650.00 12. Net Pymt. this Estimate 29,942.26