Dept. of Trans. PROGRESS Serial No. Contract No. 05-116-10-19 12-0C9874 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 68% 52% 12-ORA-73-12.5/21.6 Federal Project: ACNH-P079(70) Progress payment No. 06 Payment period ending: 04-20-05 D W POWELL CONSTRUCTION INC P O BOX 1406 FONTANA CA 923341406 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 618,690.80 52,348.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 0.00 -20,824.22 4. Earned Subject to Retention 618,690.80 31,523.78 5. Mobilization 95,000.00 0.00 6. Total Work Completed 713,690.80 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 713,690.80 31,523.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 31,523.78