Dept. of Trans. PROGRESS Serial No. Contract No. 05-053-13-12 12-0C9874 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 62% 31% 12-ORA-73-12.5/21.6 Federal Project: ACNH-P079(70) Progress payment No. 04 Payment period ending: 02-20-05 D W POWELL CONSTRUCTION INC P O BOX 1406 FONTANA CA 923341406 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 553,284.00 17,638.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 16,710.39 16,710.39 4. Earned Subject to Retention 569,994.39 34,348.39 5. Mobilization 95,000.00 0.00 6. Total Work Completed 648,284.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 664,994.39 34,348.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 34,348.39