Dept. of Trans. PROGRESS Serial No. Contract No. 07-115-10-00 12-043214 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 18% 7% 12-ORA-74-13.3/16.6 Federal Project: ACST-P074(50) P-P074(50) Progress payment No. 03 Payment period ending: 04-20-07 BRENT ENGINEERING INC 81 SHIELD IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,139,128.65 2,238,415.30 2.a. Extra Work 84,800.01 -11,613.70 b. Adjustment Comp. 3. Materials on Hand 1,348,359.34 -13,562.96 4. Earned Subject to Retention 4,572,288.00 2,213,238.64 5. Mobilization 2,700,000.00 900,000.00 6. Total Work Completed 5,923,928.66 7. Deductions -246,757.44 -82,252.48 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,025,530.56 3,030,986.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,030,986.16