Dept. of Trans. PROGRESS Serial No. Contract No. 09-202-14-40 11-2T0934 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 51% 44% 11-SD-15-M16.0/M19.3 Federal Project: NONE Progress payment No. 20 Payment period ending: 07-20-09 FLATIRON WEST, INC. 1770 LA COSTA MEADOWS DRIVE SAN MARCOS CA 92078 Escrow No. 02370 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,107,069.69 2,500,007.46 2.a. Extra Work 804,697.67 69,068.09 b. Adjustment Comp. 336,200.69 0.00 3. Materials on Hand 979,354.19 -48,905.32 4. Earned Subject to Retention 30,227,322.24 2,520,170.23 5. Mobilization 6,298,500.00 0.00 6. Total Work Completed 35,546,468.05 7. Deductions -158,657.67 -2,000.00 8. a.Contract Retentions -1,511,366.11 -126,008.51 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 34,855,798.46 2,392,161.72 10. Reduction Amt to Escrow 11. Payment to Escrow 1,511,360.00 12. Net Pymt. this Estimate 2,392,161.72