Dept. of Trans. PROGRESS Serial No. Contract No. 11-236-11-03 11-289704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 88% 100% 11-SD-15-R42.5/R45.9 Federal Project: IM-154(206) Progress payment No. 05 Payment period ending: 08-20-11 CSI / SJH A JOINT VENTURE 9685 VIA EXCELENCIA ST. 200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,144,256.25 1,755,528.05 2.a. Extra Work 6,243.52 -27.15 b. Adjustment Comp. 71,370.80 3,820.26 3. Materials on Hand 4. Earned Subject to Retention 4,221,870.57 1,759,321.16 5. Mobilization 509,851.00 25,492.55 6. Total Work Completed 4,731,721.57 7. Deductions -7,500.00 -2,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,724,221.57 1,782,813.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,782,813.71