Dept. of Trans. PROGRESS Serial No. Contract No. 09-083-14-17 11-2772U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 100% 11-SD-75-17.4/R20.5 Federal Project: NONE Progress payment No. 05 Payment period ending: 03-20-09 VALLEY SLURRY SEAL COMPANY P O BOX 981330 WEST SACRAMENTO CA 95798 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 694,809.52 -1,083.60 2.a. Extra Work 88,944.30 80,086.45 b. Adjustment Comp. -5,466.30 0.00 3. Materials on Hand 4. Earned Subject to Retention 778,287.52 79,002.85 5. Mobilization 6. Total Work Completed 778,287.52 7. Deductions -14,040.41 0.00 8. a.Contract Retentions -38,914.38 -3,728.49 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 725,332.73 75,274.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 75,274.36