Dept. of Trans. PROGRESS Serial No. Contract No. 07-233-15-35 11-273604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 18% 15% 11-SD-805-11.4/11.4 Federal Project: NONE Progress payment No. 01 Payment period ending: 08-20-07 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 72,372.15 72,372.15 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 38,477.52 38,477.52 4. Earned Subject to Retention 110,849.67 110,849.67 5. Mobilization 45,000.00 45,000.00 6. Total Work Completed 117,372.15 7. Deductions 8. a.Contract Retentions -11,084.97 -11,084.97 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 144,764.70 144,764.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 144,764.70