Dept. of Trans. FINAL Serial No. Contract No. 06-339-10-24 11-263504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-IMP-8-R96.2/R96.8 Federal Project: ACST-008-2(100) PE-008-2(100) Progress payment No. 06 Payment period ending: 07-21-06 3 D ENTERPRISES INCORPORATED 2180 GARNET AVENUE STE 2C SAN DIEGO CA 92109 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 605,959.85 2,001.00 2.a. Extra Work 10,970.31 2,970.31 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 616,930.16 4,971.31 5. Mobilization 73,936.00 0.00 6. Total Work Completed 690,866.16 7. Deductions 0.00 20,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 690,866.16 24,971.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 24,971.31