Dept. of Trans. PROGRESS Serial No. Contract No. 05-297-14-58 11-261104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 43% 27% 11-IMP-86-9.8/19.5 Federal Project: NONE Progress payment No. 06 Payment period ending: 10-20-05 GRAHAM CONTRACTORS INC P O BOX 26770 SAN JOSE CA 95159 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 308,844.63 17,469.72 2.a. Extra Work 39,189.89 31,140.96 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 348,034.52 48,610.68 5. Mobilization 28,262.50 0.00 6. Total Work Completed 376,297.02 7. Deductions -33,957.78 -1,746.97 8. a.Contract Retentions -19,478.22 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 322,861.02 46,863.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 46,863.71