Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 04-174-12-12 11-245404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-5-R14.1/ .0 Federal Project: ACST-X073(67) PE-X073(67) Progress payment No. 06 Payment period ending: 05-03-04 A AND B LANDSCAPING P O BOX 720322 SAN DIEGO CA 92172 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 503,614.10 0.00 2.a. Extra Work 64,271.71 37,903.51 b. Adjustment Comp. -1,170.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 566,715.81 37,903.51 5. Mobilization 40,000.00 0.00 6. Total Work Completed 606,715.81 7. Deductions -21,000.00 0.00 8. a.Contract Retentions -22,348.85 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 22,348.85 0.00 9. Total pay to Contractor 585,715.81 37,903.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 37,903.51