Dept. of Trans. PROGRESS Serial No. Contract No. 04-113-14-19 11-245404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 72% 11-SD-5-R14.1/ .0 Federal Project: ACST-X073(67) PE-X073(67) Progress payment No. 04 Payment period ending: 04-20-04 A AND B LANDSCAPING P O BOX 720322 SAN DIEGO CA 92172 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 422,932.10 2,570.00 2.a. Extra Work 25,214.80 25,214.80 b. Adjustment Comp. -1,170.00 -1,170.00 3. Materials on Hand 4. Earned Subject to Retention 446,976.90 26,614.80 5. Mobilization 40,000.00 0.00 6. Total Work Completed 486,976.90 7. Deductions -1,000.00 -1,000.00 8. a.Contract Retentions -22,348.85 -1,330.74 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 463,628.05 24,284.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 24,284.06