Dept. of Trans. PROGRESS Serial No. Contract No. 02-144-11-38 11-1993U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 77% 11-IMP-111-R8.0/R12.9 Federal Project: ACNH-P111(60) Progress payment No. 21 Payment period ending: 05-20-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01646 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,119,179.20 418,812.19 2.a. Extra Work 133,601.27 836.13 b. Adjustment Comp. -81,142.96 0.00 3. Materials on Hand 113,761.27 -140,082.66 4. Earned Subject to Retention 15,285,398.78 279,565.66 5. Mobilization 374,061.00 0.00 6. Total Work Completed 15,545,698.51 7. Deductions -144,394.19 167,830.24 8. a.Contract Retentions -764,269.94 -13,978.28 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,750,795.65 433,417.62 10. Reduction Amt to Escrow 11. Payment to Escrow 764,260.00 12. Net Pymt. this Estimate 433,417.62