Dept. of Trans. PROGRESS Serial No. Contract No. 02-023-13-54 11-066004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 59% 11-SD-94-6.2/R8.8 Federal Project: ACNH-S094(47) Progress payment No. 28 Payment period ending: 01-20-02 A AND B LANDSCAPING P O BOX 720322 SAN DIEGO CA 92172 Escrow No. 01453 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,166,545.00 1,125.00 2.a. Extra Work 89,140.85 0.00 b. Adjustment Comp. -3,801.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,251,884.85 1,125.00 5. Mobilization 90,000.00 0.00 6. Total Work Completed 1,341,884.85 7. Deductions -1,000.00 0.00 8. a.Contract Retentions -62,594.24 -56.25 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,278,290.61 1,068.75 10. Reduction Amt to Escrow 11. Payment to Escrow 62,590.00 12. Net Pymt. this Estimate 1,068.75